Tennessee Gas Pipeline Notice 394363

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/20/2025 2:38:33PM Notice End Date/Time:  04/21/2025 9:00:00am
Post Date/Time:  4/20/2025 2:38:33 PM Notice ID: 394363
Reqrd Rsp:  1 Rsp Date:  04/20/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-21-2025 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Monday, April 21, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 66,420 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP due to operational concerns; 5,000 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 39% of SIPss due to nominations in excess of operational capacity; 42,500 Dths

·         Arlington Storage Delivery Meter (Pin 412803) - through 100% of IT due to operational concerns; 163,747 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 41% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 57,242 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths

·         STA 307 (Segment 307 BH) - through approx 92% of SOP due to nominations in excess of operational capacity; 374,751 Dths

·         MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 502,655 Dths

·         STA 315 (Segment 315 BH) - through approx 87% of SOP due to nominations in excess of operational capacity; 614,126 Dths

·         STA 321 (Segment 321 FH) - through approx 75% of SOP due to emergent repair at STA 321 Unit 5B; 734,073 Dths

·         MLV 330 (Segment 324 FH) - through approx 20% of SOP due to nominations in excess of operational capacity; 89,379 Dths

·         MLV 336 East (Segment 336 FH) - through approx 29% of SOP due to nominations in excess of operational capacity; 26,826 Dths

·         Z5hc North (Segment 299 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 725,890 Dths

·         STA 245 (Segment 245 FH) - through approx 76% of SOP due to nominations in excess of operational capacity; 794,417 Dths

·         STA 249 (Segment 249 FH) - through approx 54% of SOP due to nominations in excess of operational capacity; 383,010 Dths

·         MLV 273 (Segment 284 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 263,323 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/20/2025 2:38:33PM Notice End Date/Time:  04/21/2025 9:00:00am
Post Date/Time:  4/20/2025 2:38:33 PM Notice ID: 394363
Reqrd Rsp:  1 Rsp Date:  04/20/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-21-2025 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Monday, April 21, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 66,420 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP due to operational concerns; 5,000 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 39% of SIPss due to nominations in excess of operational capacity; 42,500 Dths

·         Arlington Storage Delivery Meter (Pin 412803) - through 100% of IT due to operational concerns; 163,747 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 41% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 57,242 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths

·         STA 307 (Segment 307 BH) - through approx 92% of SOP due to nominations in excess of operational capacity; 374,751 Dths

·         MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 502,655 Dths

·         STA 315 (Segment 315 BH) - through approx 87% of SOP due to nominations in excess of operational capacity; 614,126 Dths

·         STA 321 (Segment 321 FH) - through approx 75% of SOP due to emergent repair at STA 321 Unit 5B; 734,073 Dths

·         MLV 330 (Segment 324 FH) - through approx 20% of SOP due to nominations in excess of operational capacity; 89,379 Dths

·         MLV 336 East (Segment 336 FH) - through approx 29% of SOP due to nominations in excess of operational capacity; 26,826 Dths

·         Z5hc North (Segment 299 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 725,890 Dths

·         STA 245 (Segment 245 FH) - through approx 76% of SOP due to nominations in excess of operational capacity; 794,417 Dths

·         STA 249 (Segment 249 FH) - through approx 54% of SOP due to nominations in excess of operational capacity; 383,010 Dths

·         MLV 273 (Segment 284 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 263,323 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.