Tennessee Gas Pipeline Notice 394361

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/20/2025 11:43:19AM Notice End Date/Time:  04/21/2025 9:00:00am
Post Date/Time:  4/20/2025 11:43:19 AM Notice ID: 394361
Reqrd Rsp:  1 Rsp Date:  04/20/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-20-2025 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Sunday, April 20, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEMWIDE (EXCLUDING ALL AREAS SOUTH OF STA 1) FOR UNDER-TAKES FROM THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

METER RESTRICTIONS

·         Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to operational concerns; 70,000 Dths

·         Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 5,000 Dths

·         TRNSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

·         Arlington Storage Delivery Meter (Pin 412803) - through 100% of IT increases due to operational concerns; 41,947 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 66,527 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 374,751 Dths

·         MLV 314 East (Segment 314 BH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 266,699 Dths

·         STA 315 (Segment 315 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 244,838 Dths

·         STA 321 (Segment 321 FH) - through approx 84% of SOP increases due to nominations in excess of operational capacity and due to an emergent repair at STA 321 UNIT 5B; 155,083 Dths

·         Z5 HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 291,701 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 306,492 Dths

·         STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 163,068 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 170,854 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/20/2025 11:43:19AM Notice End Date/Time:  04/21/2025 9:00:00am
Post Date/Time:  4/20/2025 11:43:19 AM Notice ID: 394361
Reqrd Rsp:  1 Rsp Date:  04/20/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-20-2025 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Sunday, April 20, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 SYSTEMWIDE (EXCLUDING ALL AREAS SOUTH OF STA 1) FOR UNDER-TAKES FROM THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

METER RESTRICTIONS

·         Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to operational concerns; 70,000 Dths

·         Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 5,000 Dths

·         TRNSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

·         Arlington Storage Delivery Meter (Pin 412803) - through 100% of IT increases due to operational concerns; 41,947 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 66,527 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 374,751 Dths

·         MLV 314 East (Segment 314 BH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 266,699 Dths

·         STA 315 (Segment 315 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 244,838 Dths

·         STA 321 (Segment 321 FH) - through approx 84% of SOP increases due to nominations in excess of operational capacity and due to an emergent repair at STA 321 UNIT 5B; 155,083 Dths

·         Z5 HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 291,701 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 306,492 Dths

·         STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 163,068 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 170,854 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.