-Restrictions to Primary In-Path
transportation services may be necessary.
|
|
|
|
SNG - Outage
Impact Report
|
|
|
|
|
-Restrictions to In-Path
transportation services may be necessary.
|
|
|
|
Seven Day Forecast (updated 10/29/26)
|
|
|
|
-Restrictions to Interruptible and Out of Path transportation services may be necessary.
|
|
|
|
|
|
|
|
-No anticipated impact
to transportation services.
|
|
Station
/ Seg
|
Est Nominal
Design Capacity (Thousand Dth)
|
Monday (11/2)
|
Tuesday (11/3)
|
Wednesday (11/4)
|
Thursday (11/5)
|
Friday (11/6)
|
Saturday (11/7)
|
Sunday (11/8)
|
Primary Outage(s) that may Impact Throughput
|
|
Est. Operational Capacity (Operational Impact) - Thousand Dth
|
|
Onward (segment 30)
|
209
|
209
|
209
|
209
|
209
|
209
|
209
|
209
|
|
|
Duncanville Lateral
(segment 90)
|
36
|
36
|
36
|
36
|
36
|
36
|
36
|
36
|
|
|
Dearmanville (segment 150)
|
355
|
335
(20)
|
335
(20)
|
335
(20)
|
335
(20)
|
355
|
355
|
355
|
Bell Mills
Compressor Station: Scheduled Unit Maintenance Proj-4500-3 (11/2/2026 - 11/5/2026)
|
|
White Castle
(segment 340)
|
798
|
738
(60)
|
548
(250)
|
673
(125)
|
673
(125)
|
673
(125)
|
738
(60)
|
738
(60)
|
Shadyside Compressor Station:
Scheduled Station Maintenance Proj-5000 (11/3/2026)
Shadyside Compressor Station: Scheduled Unit Maintenance Proj-5000-2 (11/4/2026
- 11/6/2026)
Shadyside Compressor Station: Scheduled Unit Maintenance Proj-5000-4-5 (11/3/2026)
Shadyside Compressor Station: Scheduled Unit Maintenance Proj-5000-5 (11/1/2026
- 11/20/2026)
|
|
LA West Leg (segment 350)
|
798
|
733
(65)
|
733
(65)
|
733
(65)
|
733
(65)
|
733
(65)
|
733
(65)
|
733
(65)
|
Franklinton Compressor Station: Scheduled Unit
Maintenance Proj-512215 (11/1/2026 - 11/8/2026)
|
|
Sesh (segment 380)
|
507
|
507
|
507
|
507
|
507
|
507
|
507
|
507
|
|
|
Gwinville (segment 400)
|
234
|
234
|
234
|
234
|
234
|
234
|
234
|
234
|
|
|
Bay Springs
(segment 420)
|
1,817
|
1702
(115)
|
1702
(115)
|
1702
(115)
|
1702
(115)
|
1702
(115)
|
1702
(115)
|
1702
(115)
|
Bay Springs Compressor Station:
Scheduled Unit Maintenance Proj-5216-1 (11/1/2026 - 3/31/2027)
|
|
Enterprise (segment 430)
|
2,450
|
2195
(255)
|
2195
(255)
|
2195
(255)
|
2195
(255)
|
2195
(255)
|
2195
(255)
|
2195
(255)
|
Enterprise Compressor Station: Scheduled Unit Maintenance Proj-5222-15 (11/1/2026
- 11/15/2026)
South
Main line east of Enterprise: Unscheduled Pipeline Maintenance - CAO (11/1/2026
- 3/31/2027)
|
|
York
'ZONE 1/2 BOUNDARY'
(segment 440)
|
2,449
|
2194
(255)
|
2194
(255)
|
2194
(255)
|
2194
(255)
|
2194
(255)
|
2194
(255)
|
2194
(255)
|
York Compressor Station: Scheduled Unit Maintenance Proj-5230-1 (11/1/2026 - 11/15/2026)
|
|
Ellerslie (segment 490)
|
1,663
|
1608
(55)
|
1608
(55)
|
1608
(55)
|
1608
(55)
|
1608
(55)
|
1608
(55)
|
1608
(55)
|
Thomaston Compressor Station: Scheduled Unit
Maintenance Proj-5272-5 (11/2/2026 - 12/6/2026)
|
|
South Atlanta
(segment 510)
|
537
|
537
|
537
|
537
|
537
|
537
|
537
|
537
|
|
|
Thomaston East (segment 530)
|
900
|
900
|
900
|
900
|
900
|
900
|
900
|
900
|
|
|
Ocmulgee (segment 530)
|
801
|
721
(80)
|
721
(80)
|
721
(80)
|
721
(80)
|
721
(80)
|
721
(80)
|
721
(80)
|
Ocmulgee Compressor Station: Unscheduled Unit
Outage Proj-5277-4 (11/1/2026 - 11/15/2026)
|
|
South Georgia
(segment 650)
|
143
|
143
|
143
|
143
|
143
|
143
|
143
|
143
|
|
|
This document is updated on a
weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event
of conflicts between DART posted dates and dates on this report.
The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
|