Southern Natural Gas Notice 712277
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Update
to Scheduled Pipeline Maintenance – North Main loop line east of Providence
(Segment 130 – Tarrant)
The scheduled pipeline maintenance on the North Main loop line east of
Providence compressor station (Segment 130 – Tarrant) located in Jefferson
County, AL, referenced on Southern's weekly EBB maintenance postings scheduled
from July 6, 2026, to August 14, 2026, remains on-going and has been extended
through August 21, 2026. As a result, Segment 130 (Tarrant) capacity of 563 Mdth/d
will remain impacted by 125 Mdth/d through
gas day, Friday, August 21, 2026. Based on
current system demand, an impact to Interruptible and Out of Path nominations
may become necessary.
Please continue to reference our weekly EBB postings for current maintenance information. If you have any questions, please contact your Scheduling Representative or Account Manager.
SNG Gas Control
Update
to Scheduled Pipeline Maintenance – North Main loop line east of Providence
(Segment 130 – Tarrant)
The scheduled pipeline maintenance on the North Main loop line east of
Providence compressor station (Segment 130 – Tarrant) located in Jefferson
County, AL, referenced on Southern's weekly EBB maintenance postings scheduled
from July 6, 2026, to August 14, 2026, remains on-going and has been extended
through August 21, 2026. As a result, Segment 130 (Tarrant) capacity of 563 Mdth/d
will remain impacted by 125 Mdth/d through
gas day, Friday, August 21, 2026. Based on
current system demand, an impact to Interruptible and Out of Path nominations
may become necessary.
Please continue to reference our weekly EBB postings for current maintenance information. If you have any questions, please contact your Scheduling Representative or Account Manager.
SNG Gas Control