Southern Natural Gas Notice 711922

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  6900518-SOUTHERN NATURAL GAS CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  04/23/2026 2:38:43PM Notice End Date/Time:  04/24/2026 9:00:00am
Post Date/Time:  4/23/2026 2:38:43 PM Notice ID: 711922
Reqrd Rsp:  1 Rsp Date:  04/23/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Outage Impact Report
Notice Text:

 

 

 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

 

SNG - Outage Impact Report

 

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

Seven Day Forecast (updated 04/23/26)

 

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

 

-No anticipated impact to transportation services.

 

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

 

Monday (4/27)

 

Tuesday (4/28)

 

Wednesday (4/29)

 

Thursday (4/30)

 

Friday (5/1)

 

Saturday (5/2)

 

Sunday (5/3)

 

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Bessemer Calera (segment 120)

 

 

100

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

Bessemer Calera Line north of Helena Regulator: Scheduled Pipeline Maintenance Proj-SNG-38163(PT) (4/1/2026 - 5/18/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance Proj-52161 (7/8/2025 - 10/31/2026)

 

 

Enterprise (segment 430)

 

 

2,306

 

 

2131

(175)

 

 

2131

(175)

 

 

2131

(175)

 

 

2191

(115)

 

 

2191

(115)

 

 

2191

(115)

 

 

2191

(115)

Enterprise Compressor Station: Scheduled Unit Maintenance Proj-522212 (3/16/2026 - 5/15/2026)

Enterprise Compressor Station: Scheduled Unit Maintenance Proj-5222-16 (4/20/2026 - 4/29/2026)

South Main 2nd loop line east of Enterprise: Scheduled Pipeline Maintenance Proj-SNG-8792 (4/24/2026 - 5/3/2026)

 

Gallion (Segment 440)

 

 

2,300

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

Gallion Compressor Station: Scheduled Unit Maintenance Proj-52369 (4/27/2026 - 5/10/2026)

 

Selma (segment 460)

 

 

2,293

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

Selma Compressor Station: Unscheduled Unit Maintenance Proj-52301 (12/22/2025 - 5/31/2026)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

Thomaston West (segment 490)

 

 

1,535

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

Thomaston Compressor Station: Scheduled Unit Maintenance Proj-5272-5 (4/27/2026 - 5/11/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

Ocmulgee (segment 530)

 

 

804

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

Ocmulgee Compressor Station: Scheduled Unit Maintenance Proj-52775 (4/6/2026 - 5/24/2026)

 

Hall Gate (segment 560)

 

 

705

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

Hall Gate Compressor Station: Scheduled Unit Maintenance Proj-52833 (4/20/2026 - 5/24/2026)

Hall Gate Compressor Station: Unscheduled Unit Outage Proj-5283-1 (4/22/2026 - 5/3/2026)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

May 2026 (updated 04/23/26)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (5/4 - 5/10)

Week 2 (5/11 - 5/17)

Week 3 (5/18 - 5/24)

Week 4 (5/25 - 5/31)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Bessemer Calera (segment 120)

 

 

100

 

82

(18)

 

82

(18)

 

82

(18)

 

 

100

Bessemer Calera Line north of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (4/1/2026 - 5/18/2026)

 

Helena Regulator (segment 120)

 

 

21

 

 

21

 

 

21

 

 

21

 

18

(3)

Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (5/25/2026 - 7/4/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

 

 

Sesh (segment 380)

 

 

 

500

 

 

407

(93)

 

 

451

(49)

 

 

448

(52)

 

 

 

500

SESH: Scheduled Maintenance (M) (5/11/2026) SESH: Scheduled Maintenance (M) (5/12/2026) SESH: Scheduled Maintenance (M) (5/17/2026)

SESH: Scheduled Maintenance (M) (5/18/2026 - 5/22/2026) SESH: Scheduled Maintenance (M) (5/23/2026) SESH: Scheduled Maintenance (M) (5/4/2026)

SESH: Scheduled Maintenance (M) (5/5/2026) SESH: Scheduled Maintenance (M) (5/6/2026)

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

2236

(70)

 

2236

(70)

 

2126

(180)

 

2126

(180)

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522212 (3/16/2026 - 5/15/2026)

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522215 (5/18/2026 - 6/21/2026)

 

York (segment 440)

 

 

2,305

 

 

2,305

 

 

2,305

 

2080

(225)

 

 

2,305

York Compressor Station: Scheduled Unit Maintenance, Proj-52303 (5/21/2026 - 5/23/2026)

 

Gallion (Segment 440)

 

 

2,300

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

 

2,300

Gallion Compressor Station: Scheduled Unit Maintenance, Proj-52368 (5/11/2026 - 5/21/2026) Gallion Compressor Station: Scheduled Unit Maintenance, Proj-52369 (4/27/2026 - 5/10/2026)

 

Selma (segment 460)

 

 

2,293

 

2128

(165)

 

2128

(165)

 

2003

(290)

 

2128

(165)

Selma Compressor Station: Scheduled Unit Maintenance, Proj-52453 (5/18/2026 - 5/20/2026) Selma Compressor Station: Unscheduled Unit Maintenance, Proj-52301 (12/22/2025 - 5/31/2026)

 

Elmore (segment 460)

 

 

2,010

 

 

2,010

 

1755

(255)

 

 

2,010

 

 

2,010

Elmore Compressor Station: Scheduled Unit Maintenance, Proj-525112 (5/14/2026 - 5/16/2026)

 

Auburn (segment 460)

 

 

1,953

 

 

1,953

 

1698

(255)

 

1738

(215)

 

1848

(105)

Auburn Compressor Station: Scheduled Unit Maintenance, Proj-52593 (5/11/2026 - 5/13/2026) South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation),

Proj-SNG-20457(1) (5/18/2026 - 5/22/2026)

South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation), Proj-SNG-20457(2) (5/23/2026 - 5/29/2026)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

1402

(145)

 

 

1,547

Ellerslie Compressor Station: Scheduled Unit Maintenance , Proj-52678-9 (5/18/2026 - 5/21/2026)

 

Thomaston West (segment 490)

 

 

1,535

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

Thomaston Compressor Station: Scheduled Unit Maintenance, Proj-5272-5 (4/27/2026 - 5/11/2026)

Thomaston Compressor Station: Scheudled Unit Maintenance, Proj-52722 (5/11/2026 - 6/4/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East

(segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

Ocmulgee (segment 530)

 

 

804

 

659

(145)

 

659

(145)

 

659

(145)

 

 

804

Ocmulgee Compressor Station: Scheduled Unit Maintenance, Proj-52775 (4/6/2026 - 5/24/2026)

 

Hall Gate (segment 560)

 

 

705

 

635

(70)

 

635

(70)

 

635

(70)

 

 

705

Hall Gate Compressor Station: Scheduled Unit Maintenance, Proj-52833 (4/20/2026 - 5/24/2026)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

June 2026 (updated 04/23/26)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (6/1 - 6/7)

Week 2 (6/8 - 6/14)

Week 3 (6/15 - 6/21)

Week 4 (6/22 - 6/28)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Helena Regulator (segment 120)

 

 

21

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (5/25/2026 - 7/4/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

2126

(180)

 

2126

(180)

 

2126

(180)

 

 

2,306

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522215 (5/18/2026 - 6/21/2026)

 

York (segment 440)

 

 

2,305

 

 

2,305

 

2235

(70)

 

2235

(70)

 

 

2,305

South Main 2nd loop line east of York: Scheduled Pipeline Maintenance, Proj-SNG-36214 (6/12/2026 - 6/21/2026)

 

Auburn (segment 460)

 

 

1,953

 

1793

(160)

 

1793

(160)

 

 

1,953

 

 

1,953

South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation), Proj-SNG-22003(1) (6/1/2026 - 6/9/2026)

South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation), Proj-SNG-22003(2) (6/10/2026 - 6/14/2026)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

Thomaston West (segment 490)

 

 

1,535

 

1520

(15)

 

 

1,535

 

 

1,535

 

 

1,535

Thomaston Compressor Station: Scheudled Unit Maintenance, Proj-52722 (5/11/2026 - 6/4/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

East/South Wrens (segment 560)

 

 

680

 

 

680

 

590

(90)

 

 

680

 

 

680

Wrens Compressor Station: Scheduled Unit Maintenance, Proj-52885 (6/8/2026 - 6/10/2026)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

July 2026 (updated 04/23/26)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (6/29 - 7/5)

Week 2 (7/6 - 7/12)

Week 3 (7/13 - 7/19)

Week 4 (7/20 - 7/26)

Week 5 (7/27 - 8/2)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Helena Regulator (segment 120)

 

 

21

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (5/25/2026 - 7/4/2026)

Bessemer Calera loop line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (7/10/2026 - 8/24/2026)

 

Tarrant (segment 130)

 

 

563

 

 

563

 

543

(20)

 

543

(20)

 

543

(20)

 

543

(20)

Tarrant Compressor Station: Scheduled Unit Maintenance(panel), Proj-41527-8-9-10-11 (7/6/2026 - 9/13/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

August 2026 (updated 04/23/26)

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (8/3 - 8/9)

Week 2 (8/10 - 8/16)

Week 3 (8/17 - 8/23)

Week 4 (8/24 - 8/30)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Helena Regulator (segment 120)

 

 

21

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

Bessemer Calera loop line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (7/10/2026 - 8/24/2026)

 

Tarrant (segment 130)

 

 

563

 

543

(20)

 

543

(20)

 

543

(20)

 

543

(20)

Tarrant Compressor Station: Scheduled Unit Maintenance(panel), Proj-41527-8-9-10-11 (7/6/2026 - 9/13/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

Gallion (Segment 440)

 

 

2,300

 

 

2,300

 

 

2,300

 

 

2,300

 

 

2,300

 

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

1317

(230)

 

 

1,547

Ellerslie Compressor Station: Scheduled Station Maintenance, Proj-5267 (8/18/2026 - 8/20/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.

 

TSP/TSP Name:  6900518-SOUTHERN NATURAL GAS CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  04/23/2026 2:38:43PM Notice End Date/Time:  04/24/2026 9:00:00am
Post Date/Time:  4/23/2026 2:38:43 PM Notice ID: 711922
Reqrd Rsp:  1 Rsp Date:  04/23/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Outage Impact Report
Notice Text:

 

 

 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

 

SNG - Outage Impact Report

 

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

Seven Day Forecast (updated 04/23/26)

 

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

 

-No anticipated impact to transportation services.

 

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

 

Monday (4/27)

 

Tuesday (4/28)

 

Wednesday (4/29)

 

Thursday (4/30)

 

Friday (5/1)

 

Saturday (5/2)

 

Sunday (5/3)

 

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Bessemer Calera (segment 120)

 

 

100

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

 

82

(18)

Bessemer Calera Line north of Helena Regulator: Scheduled Pipeline Maintenance Proj-SNG-38163(PT) (4/1/2026 - 5/18/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance Proj-52161 (7/8/2025 - 10/31/2026)

 

 

Enterprise (segment 430)

 

 

2,306

 

 

2131

(175)

 

 

2131

(175)

 

 

2131

(175)

 

 

2191

(115)

 

 

2191

(115)

 

 

2191

(115)

 

 

2191

(115)

Enterprise Compressor Station: Scheduled Unit Maintenance Proj-522212 (3/16/2026 - 5/15/2026)

Enterprise Compressor Station: Scheduled Unit Maintenance Proj-5222-16 (4/20/2026 - 4/29/2026)

South Main 2nd loop line east of Enterprise: Scheduled Pipeline Maintenance Proj-SNG-8792 (4/24/2026 - 5/3/2026)

 

Gallion (Segment 440)

 

 

2,300

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

2255

(45)

Gallion Compressor Station: Scheduled Unit Maintenance Proj-52369 (4/27/2026 - 5/10/2026)

 

Selma (segment 460)

 

 

2,293

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

 

2128

(165)

Selma Compressor Station: Unscheduled Unit Maintenance Proj-52301 (12/22/2025 - 5/31/2026)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

Thomaston West (segment 490)

 

 

1,535

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

Thomaston Compressor Station: Scheduled Unit Maintenance Proj-5272-5 (4/27/2026 - 5/11/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

Ocmulgee (segment 530)

 

 

804

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

 

659

(145)

Ocmulgee Compressor Station: Scheduled Unit Maintenance Proj-52775 (4/6/2026 - 5/24/2026)

 

Hall Gate (segment 560)

 

 

705

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

 

560

(145)

Hall Gate Compressor Station: Scheduled Unit Maintenance Proj-52833 (4/20/2026 - 5/24/2026)

Hall Gate Compressor Station: Unscheduled Unit Outage Proj-5283-1 (4/22/2026 - 5/3/2026)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

May 2026 (updated 04/23/26)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (5/4 - 5/10)

Week 2 (5/11 - 5/17)

Week 3 (5/18 - 5/24)

Week 4 (5/25 - 5/31)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Bessemer Calera (segment 120)

 

 

100

 

82

(18)

 

82

(18)

 

82

(18)

 

 

100

Bessemer Calera Line north of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (4/1/2026 - 5/18/2026)

 

Helena Regulator (segment 120)

 

 

21

 

 

21

 

 

21

 

 

21

 

18

(3)

Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (5/25/2026 - 7/4/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

 

 

Sesh (segment 380)

 

 

 

500

 

 

407

(93)

 

 

451

(49)

 

 

448

(52)

 

 

 

500

SESH: Scheduled Maintenance (M) (5/11/2026) SESH: Scheduled Maintenance (M) (5/12/2026) SESH: Scheduled Maintenance (M) (5/17/2026)

SESH: Scheduled Maintenance (M) (5/18/2026 - 5/22/2026) SESH: Scheduled Maintenance (M) (5/23/2026) SESH: Scheduled Maintenance (M) (5/4/2026)

SESH: Scheduled Maintenance (M) (5/5/2026) SESH: Scheduled Maintenance (M) (5/6/2026)

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

2236

(70)

 

2236

(70)

 

2126

(180)

 

2126

(180)

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522212 (3/16/2026 - 5/15/2026)

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522215 (5/18/2026 - 6/21/2026)

 

York (segment 440)

 

 

2,305

 

 

2,305

 

 

2,305

 

2080

(225)

 

 

2,305

York Compressor Station: Scheduled Unit Maintenance, Proj-52303 (5/21/2026 - 5/23/2026)

 

Gallion (Segment 440)

 

 

2,300

 

2255

(45)

 

2255

(45)

 

2255

(45)

 

 

2,300

Gallion Compressor Station: Scheduled Unit Maintenance, Proj-52368 (5/11/2026 - 5/21/2026) Gallion Compressor Station: Scheduled Unit Maintenance, Proj-52369 (4/27/2026 - 5/10/2026)

 

Selma (segment 460)

 

 

2,293

 

2128

(165)

 

2128

(165)

 

2003

(290)

 

2128

(165)

Selma Compressor Station: Scheduled Unit Maintenance, Proj-52453 (5/18/2026 - 5/20/2026) Selma Compressor Station: Unscheduled Unit Maintenance, Proj-52301 (12/22/2025 - 5/31/2026)

 

Elmore (segment 460)

 

 

2,010

 

 

2,010

 

1755

(255)

 

 

2,010

 

 

2,010

Elmore Compressor Station: Scheduled Unit Maintenance, Proj-525112 (5/14/2026 - 5/16/2026)

 

Auburn (segment 460)

 

 

1,953

 

 

1,953

 

1698

(255)

 

1738

(215)

 

1848

(105)

Auburn Compressor Station: Scheduled Unit Maintenance, Proj-52593 (5/11/2026 - 5/13/2026) South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation),

Proj-SNG-20457(1) (5/18/2026 - 5/22/2026)

South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation), Proj-SNG-20457(2) (5/23/2026 - 5/29/2026)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

1402

(145)

 

 

1,547

Ellerslie Compressor Station: Scheduled Unit Maintenance , Proj-52678-9 (5/18/2026 - 5/21/2026)

 

Thomaston West (segment 490)

 

 

1,535

 

1520

(15)

 

1520

(15)

 

1520

(15)

 

1520

(15)

Thomaston Compressor Station: Scheduled Unit Maintenance, Proj-5272-5 (4/27/2026 - 5/11/2026)

Thomaston Compressor Station: Scheudled Unit Maintenance, Proj-52722 (5/11/2026 - 6/4/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East

(segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

Ocmulgee (segment 530)

 

 

804

 

659

(145)

 

659

(145)

 

659

(145)

 

 

804

Ocmulgee Compressor Station: Scheduled Unit Maintenance, Proj-52775 (4/6/2026 - 5/24/2026)

 

Hall Gate (segment 560)

 

 

705

 

635

(70)

 

635

(70)

 

635

(70)

 

 

705

Hall Gate Compressor Station: Scheduled Unit Maintenance, Proj-52833 (4/20/2026 - 5/24/2026)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

June 2026 (updated 04/23/26)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (6/1 - 6/7)

Week 2 (6/8 - 6/14)

Week 3 (6/15 - 6/21)

Week 4 (6/22 - 6/28)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Helena Regulator (segment 120)

 

 

21

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (5/25/2026 - 7/4/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

2126

(180)

 

2126

(180)

 

2126

(180)

 

 

2,306

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522215 (5/18/2026 - 6/21/2026)

 

York (segment 440)

 

 

2,305

 

 

2,305

 

2235

(70)

 

2235

(70)

 

 

2,305

South Main 2nd loop line east of York: Scheduled Pipeline Maintenance, Proj-SNG-36214 (6/12/2026 - 6/21/2026)

 

Auburn (segment 460)

 

 

1,953

 

1793

(160)

 

1793

(160)

 

 

1,953

 

 

1,953

South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation), Proj-SNG-22003(1) (6/1/2026 - 6/9/2026)

South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation), Proj-SNG-22003(2) (6/10/2026 - 6/14/2026)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

Thomaston West (segment 490)

 

 

1,535

 

1520

(15)

 

 

1,535

 

 

1,535

 

 

1,535

Thomaston Compressor Station: Scheudled Unit Maintenance, Proj-52722 (5/11/2026 - 6/4/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

East/South Wrens (segment 560)

 

 

680

 

 

680

 

590

(90)

 

 

680

 

 

680

Wrens Compressor Station: Scheduled Unit Maintenance, Proj-52885 (6/8/2026 - 6/10/2026)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

July 2026 (updated 04/23/26)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (6/29 - 7/5)

Week 2 (7/6 - 7/12)

Week 3 (7/13 - 7/19)

Week 4 (7/20 - 7/26)

Week 5 (7/27 - 8/2)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Helena Regulator (segment 120)

 

 

21

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (5/25/2026 - 7/4/2026)

Bessemer Calera loop line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (7/10/2026 - 8/24/2026)

 

Tarrant (segment 130)

 

 

563

 

 

563

 

543

(20)

 

543

(20)

 

543

(20)

 

543

(20)

Tarrant Compressor Station: Scheduled Unit Maintenance(panel), Proj-41527-8-9-10-11 (7/6/2026 - 9/13/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

August 2026 (updated 04/23/26)

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (8/3 - 8/9)

Week 2 (8/10 - 8/16)

Week 3 (8/17 - 8/23)

Week 4 (8/24 - 8/30)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Helena Regulator (segment 120)

 

 

21

 

18

(3)

 

18

(3)

 

18

(3)

 

18

(3)

Bessemer Calera loop line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (7/10/2026 - 8/24/2026)

 

Tarrant (segment 130)

 

 

563

 

543

(20)

 

543

(20)

 

543

(20)

 

543

(20)

Tarrant Compressor Station: Scheduled Unit Maintenance(panel), Proj-41527-8-9-10-11 (7/6/2026 - 9/13/2026)

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

760

 

 

760

 

 

760

 

 

760

 

 

760

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Bay Springs (segment 420)

 

 

1,675

 

1595

(80)

 

1595

(80)

 

1595

(80)

 

1595

(80)

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

Gallion (Segment 440)

 

 

2,300

 

 

2,300

 

 

2,300

 

 

2,300

 

 

2,300

 

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

1317

(230)

 

 

1,547

Ellerslie Compressor Station: Scheduled Station Maintenance, Proj-5267 (8/18/2026 - 8/20/2026)

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.