Portland Natural Gas Transmission System Notice 5409

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP
159747872

TSP Name
Portland Natural Gas Transmission

Notice Identifier
5409

Critical Notice Description (Critical Desc)
OPER ALERT

Notice Effective Date/Time
01/24/2026 6:35 pm

Notice End Date/Time
02/28/2026 9:00 am

Prior Notice


Notice Stat Desc
Critical notice

Notice Type
Critical notice

Required Response Indicator Description
NO RESPONSE REQUIRED

Posting Date/Time
01/24/2026 6:35 pm

Subject
CRITICAL, OPERATIONAL ALERT, 20260125, PNGTS, 159747872

Notice Text
Subject: Courtesy Posting: MNUS Pipeline Conditions for 1/25/2026 

As a courtesy, Portland Natural Gas Transmission System (PNGTS) hereby notifies shippers and operators of the following notice posted by Maritimes & Northeast (M&N):  
 
For Gas Day January 25, 2026, Maritimes & Northeast (M&N) has approved and scheduled nominations at each pipeline segment and meter station up to M&N's operational capacity.  The following location has been restricted due to requested nominations exceeding M&N's operational capacity: 

M&N has scheduled and sealed nominations sourced from points north of Westbrook for delivery to points south of Westbrook.  No increases in nominations sourced from points north of Westbrook for delivery to points south of Westbrook will be accepted. 

The No Due Pipe System Wide OFO issued January 24, 2026, will remain in effect until further notice. 

Additionally, M&N requires all Power Plant Operators to provide information mandated by FERC Order No. 698 until further notice. Information required includes the hourly consumption profile of directly connected power generation facilities. 

Please contact your Operations Account Representative should you have any questions. 

 

 

TSP
159747872

TSP Name
Portland Natural Gas Transmission

Notice Identifier
5409

Critical Notice Description (Critical Desc)
OPER ALERT

Notice Effective Date/Time
01/24/2026 6:35 pm

Notice End Date/Time
02/28/2026 9:00 am

Prior Notice


Notice Stat Desc
Critical notice

Notice Type
Critical notice

Required Response Indicator Description
NO RESPONSE REQUIRED

Posting Date/Time
01/24/2026 6:35 pm

Subject
CRITICAL, OPERATIONAL ALERT, 20260125, PNGTS, 159747872

Notice Text
Subject: Courtesy Posting: MNUS Pipeline Conditions for 1/25/2026 

As a courtesy, Portland Natural Gas Transmission System (PNGTS) hereby notifies shippers and operators of the following notice posted by Maritimes & Northeast (M&N):  
 
For Gas Day January 25, 2026, Maritimes & Northeast (M&N) has approved and scheduled nominations at each pipeline segment and meter station up to M&N's operational capacity.  The following location has been restricted due to requested nominations exceeding M&N's operational capacity: 

M&N has scheduled and sealed nominations sourced from points north of Westbrook for delivery to points south of Westbrook.  No increases in nominations sourced from points north of Westbrook for delivery to points south of Westbrook will be accepted. 

The No Due Pipe System Wide OFO issued January 24, 2026, will remain in effect until further notice. 

Additionally, M&N requires all Power Plant Operators to provide information mandated by FERC Order No. 698 until further notice. Information required includes the hourly consumption profile of directly connected power generation facilities. 

Please contact your Operations Account Representative should you have any questions.