Portland Natural Gas Transmission System Notice 5037
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP
159747872
TSP Name
Portland Natural Gas Transmission
Notice Identifier
5037
Critical Notice Description (Critical Desc)
OFO
Notice Effective Date/Time
07/16/2025 9:00 am
Notice End Date/Time
08/17/2025 12:00 am
Prior Notice
Notice Stat Desc
Critical notice
Notice Type
Critical notice
Required Response Indicator Description
NO RESPONSE REQUIRED
Posting Date/Time
07/16/2025 12:26 pm
Subject
CRITICAL, OFO, 20250716, PNGTS, 159747872
Notice Text
Subject: Courtesy Posting: MNUS Operational Flow Order -- EFF 7/16
As a courtesy, Portland Natural Gas Transmission System (PNGTS) hereby notifies shippers and operators of the following notice posted by Maritimes & Northeast (M&N):
Maritimes & Northeast (M&N) has limited operational flexibility to manage imbalances. Therefore, in order to maintain the operational integrity of the system, M&N is issuing an Operational Flow Order (OFO) pursuant to Section 10.4 of the General Terms and Conditions of M&N's FERC Gas Tariff, effective immediately, for certain delivery point parties on the M&N system. M&N will be contacting the affected parties.
This OFO does not affect the ability of M&N to receive or deliver quantities of gas for scheduled nominations to any customer or pipeline.
During the effectiveness of this OFO, the notified party must be balanced such that actual deliveries of gas out of the system must be equal to or less than scheduled deliveries out of the system for the associated meter on the OBA contract. The penalty shall apply to each dekatherm of actual delivery quantities that exceeds the greater of 500 Dth or 102% of scheduled delivery quantities. The penalty will be equal to three times the arithmetic average of daily Platts Gas Daily "Daily Price Survey" posting for the High Common price for the "Tennessee, zone 6 delivery", as defined in Section 10.8(b) of the General Terms and Conditions of M&N's FERC Gas Tariff for the day on which such violation occurred. In addition, M&N will not permit retroactive nominations to avoid an OFO penalty.
This OFO will remain in effect until 9:00 AM CCT, July 17, 2025.
As a reminder, the previously posted system wide Operational Flow Order will be effective 9:00 AM CCT, July 17, 2025.
Please refer to the table below for the effected M&N operational areas, dates, and tolerance percentages:
Operational Area – System Wide:
Gas Day July 15 - 16: No OFO
Gas Day July 17 until further notice: No Due Pipe OFO 2% / 500
Operational Area – Customer Specific
Gas Day July 16: No Due Pipe OFO 2%/500
Gas Day July 17 until further notice: No Customer specific OFO
NOTE:
Deliveries No DP : Shippers are not to take more than scheduled
Deliveries No DS : Shippers are not to take less than scheduled
Receipts No DP : Shippers are not to give less than scheduled
Receipts No DS : Shippers are not to give more than scheduled
Please contact your Operations Account Representative should you have any questions.
159747872
TSP Name
Portland Natural Gas Transmission
Notice Identifier
5037
Critical Notice Description (Critical Desc)
OFO
Notice Effective Date/Time
07/16/2025 9:00 am
Notice End Date/Time
08/17/2025 12:00 am
Prior Notice
Notice Stat Desc
Critical notice
Notice Type
Critical notice
Required Response Indicator Description
NO RESPONSE REQUIRED
Posting Date/Time
07/16/2025 12:26 pm
Subject
CRITICAL, OFO, 20250716, PNGTS, 159747872
Notice Text
Subject: Courtesy Posting: MNUS Operational Flow Order -- EFF 7/16
As a courtesy, Portland Natural Gas Transmission System (PNGTS) hereby notifies shippers and operators of the following notice posted by Maritimes & Northeast (M&N):
Maritimes & Northeast (M&N) has limited operational flexibility to manage imbalances. Therefore, in order to maintain the operational integrity of the system, M&N is issuing an Operational Flow Order (OFO) pursuant to Section 10.4 of the General Terms and Conditions of M&N's FERC Gas Tariff, effective immediately, for certain delivery point parties on the M&N system. M&N will be contacting the affected parties.
This OFO does not affect the ability of M&N to receive or deliver quantities of gas for scheduled nominations to any customer or pipeline.
During the effectiveness of this OFO, the notified party must be balanced such that actual deliveries of gas out of the system must be equal to or less than scheduled deliveries out of the system for the associated meter on the OBA contract. The penalty shall apply to each dekatherm of actual delivery quantities that exceeds the greater of 500 Dth or 102% of scheduled delivery quantities. The penalty will be equal to three times the arithmetic average of daily Platts Gas Daily "Daily Price Survey" posting for the High Common price for the "Tennessee, zone 6 delivery", as defined in Section 10.8(b) of the General Terms and Conditions of M&N's FERC Gas Tariff for the day on which such violation occurred. In addition, M&N will not permit retroactive nominations to avoid an OFO penalty.
This OFO will remain in effect until 9:00 AM CCT, July 17, 2025.
As a reminder, the previously posted system wide Operational Flow Order will be effective 9:00 AM CCT, July 17, 2025.
Please refer to the table below for the effected M&N operational areas, dates, and tolerance percentages:
Operational Area – System Wide:
Gas Day July 15 - 16: No OFO
Gas Day July 17 until further notice: No Due Pipe OFO 2% / 500
Operational Area – Customer Specific
Gas Day July 16: No Due Pipe OFO 2%/500
Gas Day July 17 until further notice: No Customer specific OFO
NOTE:
Deliveries No DP : Shippers are not to take more than scheduled
Deliveries No DS : Shippers are not to take less than scheduled
Receipts No DP : Shippers are not to give less than scheduled
Receipts No DS : Shippers are not to give more than scheduled
Please contact your Operations Account Representative should you have any questions.
TSP
159747872
TSP Name
Portland Natural Gas Transmission
Notice Identifier
5037
Critical Notice Description (Critical Desc)
OFO
Notice Effective Date/Time
07/16/2025 9:00 am
Notice End Date/Time
08/17/2025 12:00 am
Prior Notice
Notice Stat Desc
Critical notice
Notice Type
Critical notice
Required Response Indicator Description
NO RESPONSE REQUIRED
Posting Date/Time
07/16/2025 12:26 pm
Subject
CRITICAL, OFO, 20250716, PNGTS, 159747872
Notice Text
Subject: Courtesy Posting: MNUS Operational Flow Order -- EFF 7/16
As a courtesy, Portland Natural Gas Transmission System (PNGTS) hereby notifies shippers and operators of the following notice posted by Maritimes & Northeast (M&N):
Maritimes & Northeast (M&N) has limited operational flexibility to manage imbalances. Therefore, in order to maintain the operational integrity of the system, M&N is issuing an Operational Flow Order (OFO) pursuant to Section 10.4 of the General Terms and Conditions of M&N's FERC Gas Tariff, effective immediately, for certain delivery point parties on the M&N system. M&N will be contacting the affected parties.
This OFO does not affect the ability of M&N to receive or deliver quantities of gas for scheduled nominations to any customer or pipeline.
During the effectiveness of this OFO, the notified party must be balanced such that actual deliveries of gas out of the system must be equal to or less than scheduled deliveries out of the system for the associated meter on the OBA contract. The penalty shall apply to each dekatherm of actual delivery quantities that exceeds the greater of 500 Dth or 102% of scheduled delivery quantities. The penalty will be equal to three times the arithmetic average of daily Platts Gas Daily "Daily Price Survey" posting for the High Common price for the "Tennessee, zone 6 delivery", as defined in Section 10.8(b) of the General Terms and Conditions of M&N's FERC Gas Tariff for the day on which such violation occurred. In addition, M&N will not permit retroactive nominations to avoid an OFO penalty.
This OFO will remain in effect until 9:00 AM CCT, July 17, 2025.
As a reminder, the previously posted system wide Operational Flow Order will be effective 9:00 AM CCT, July 17, 2025.
Please refer to the table below for the effected M&N operational areas, dates, and tolerance percentages:
Operational Area – System Wide:
Gas Day July 15 - 16: No OFO
Gas Day July 17 until further notice: No Due Pipe OFO 2% / 500
Operational Area – Customer Specific
Gas Day July 16: No Due Pipe OFO 2%/500
Gas Day July 17 until further notice: No Customer specific OFO
NOTE:
Deliveries No DP : Shippers are not to take more than scheduled
Deliveries No DS : Shippers are not to take less than scheduled
Receipts No DP : Shippers are not to give less than scheduled
Receipts No DS : Shippers are not to give more than scheduled
Please contact your Operations Account Representative should you have any questions.
159747872
TSP Name
Portland Natural Gas Transmission
Notice Identifier
5037
Critical Notice Description (Critical Desc)
OFO
Notice Effective Date/Time
07/16/2025 9:00 am
Notice End Date/Time
08/17/2025 12:00 am
Prior Notice
Notice Stat Desc
Critical notice
Notice Type
Critical notice
Required Response Indicator Description
NO RESPONSE REQUIRED
Posting Date/Time
07/16/2025 12:26 pm
Subject
CRITICAL, OFO, 20250716, PNGTS, 159747872
Notice Text
Subject: Courtesy Posting: MNUS Operational Flow Order -- EFF 7/16
As a courtesy, Portland Natural Gas Transmission System (PNGTS) hereby notifies shippers and operators of the following notice posted by Maritimes & Northeast (M&N):
Maritimes & Northeast (M&N) has limited operational flexibility to manage imbalances. Therefore, in order to maintain the operational integrity of the system, M&N is issuing an Operational Flow Order (OFO) pursuant to Section 10.4 of the General Terms and Conditions of M&N's FERC Gas Tariff, effective immediately, for certain delivery point parties on the M&N system. M&N will be contacting the affected parties.
This OFO does not affect the ability of M&N to receive or deliver quantities of gas for scheduled nominations to any customer or pipeline.
During the effectiveness of this OFO, the notified party must be balanced such that actual deliveries of gas out of the system must be equal to or less than scheduled deliveries out of the system for the associated meter on the OBA contract. The penalty shall apply to each dekatherm of actual delivery quantities that exceeds the greater of 500 Dth or 102% of scheduled delivery quantities. The penalty will be equal to three times the arithmetic average of daily Platts Gas Daily "Daily Price Survey" posting for the High Common price for the "Tennessee, zone 6 delivery", as defined in Section 10.8(b) of the General Terms and Conditions of M&N's FERC Gas Tariff for the day on which such violation occurred. In addition, M&N will not permit retroactive nominations to avoid an OFO penalty.
This OFO will remain in effect until 9:00 AM CCT, July 17, 2025.
As a reminder, the previously posted system wide Operational Flow Order will be effective 9:00 AM CCT, July 17, 2025.
Please refer to the table below for the effected M&N operational areas, dates, and tolerance percentages:
Operational Area – System Wide:
Gas Day July 15 - 16: No OFO
Gas Day July 17 until further notice: No Due Pipe OFO 2% / 500
Operational Area – Customer Specific
Gas Day July 16: No Due Pipe OFO 2%/500
Gas Day July 17 until further notice: No Customer specific OFO
NOTE:
Deliveries No DP : Shippers are not to take more than scheduled
Deliveries No DS : Shippers are not to take less than scheduled
Receipts No DP : Shippers are not to give less than scheduled
Receipts No DS : Shippers are not to give more than scheduled
Please contact your Operations Account Representative should you have any questions.