Northwest Notice 26-207
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 10/08/2026 3:18 PM MCT
Notice Eff D/T: 10/08/2026 3:18 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-207
Prior Notice: 26-204
Subject: Vernal Compressor Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-204, Northwest is
currently performing maintenance at the Vernal Compressor
Station through gas day October 19, 2026.
Primary northbound nomination requests at the Vernal CS have
exceeded the available capacity of net 0 Dth/d northbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day October 09, 2026. The Deficiency will be calculated
based on a design capacity of 353,000 Dth/d northbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 10/08/2026 3:18 PM MCT
Notice Eff D/T: 10/08/2026 3:18 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-207
Prior Notice: 26-204
Subject: Vernal Compressor Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-204, Northwest is
currently performing maintenance at the Vernal Compressor
Station through gas day October 19, 2026.
Primary northbound nomination requests at the Vernal CS have
exceeded the available capacity of net 0 Dth/d northbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day October 09, 2026. The Deficiency will be calculated
based on a design capacity of 353,000 Dth/d northbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 10/08/2026 3:18 PM MCT
Notice Eff D/T: 10/08/2026 3:18 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-207
Prior Notice: 26-204
Subject: Vernal Compressor Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-204, Northwest is
currently performing maintenance at the Vernal Compressor
Station through gas day October 19, 2026.
Primary northbound nomination requests at the Vernal CS have
exceeded the available capacity of net 0 Dth/d northbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day October 09, 2026. The Deficiency will be calculated
based on a design capacity of 353,000 Dth/d northbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 10/08/2026 3:18 PM MCT
Notice Eff D/T: 10/08/2026 3:18 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-207
Prior Notice: 26-204
Subject: Vernal Compressor Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-204, Northwest is
currently performing maintenance at the Vernal Compressor
Station through gas day October 19, 2026.
Primary northbound nomination requests at the Vernal CS have
exceeded the available capacity of net 0 Dth/d northbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day October 09, 2026. The Deficiency will be calculated
based on a design capacity of 353,000 Dth/d northbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.