Northwest Notice 26-195
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 09/23/2026 11:40 AM MCT
Notice Eff D/T: 09/23/2026 11:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-195
Prior Notice: 26-194
Subject: Mt Vernon Outage Extended Clarification
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is currently performing maintenance at the
Mt. Vernon CS (located at MP 1440.18 in Skagit County,
Washington) from Gas Day September 10, 2026, through Gas Day
September 23, 2026, and referenced in Notice ID 26-173.
However, due to delays on work, this outage has now been
extended through Gas Day September 29, 2026.
The Mt Vernon CS will continue to be limited to 1,113,000 Dth/d
southbound through the extended outage.
If primary nomination requests through the Mt Vernon CS exceeds the
available capacity of 1,113,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,277,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
Northwest Pipeline apologizes for this extended delay and is
working diligently to safely bring this station back into
service as quickly as possible to minimize any potential
impacts.
This is a superseding post of Notice ID 26-194. Northwest
incorrectly mentioned the Sumas Compressor and that is not
relevant to this maintenance update.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 09/23/2026 11:40 AM MCT
Notice Eff D/T: 09/23/2026 11:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-195
Prior Notice: 26-194
Subject: Mt Vernon Outage Extended Clarification
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is currently performing maintenance at the
Mt. Vernon CS (located at MP 1440.18 in Skagit County,
Washington) from Gas Day September 10, 2026, through Gas Day
September 23, 2026, and referenced in Notice ID 26-173.
However, due to delays on work, this outage has now been
extended through Gas Day September 29, 2026.
The Mt Vernon CS will continue to be limited to 1,113,000 Dth/d
southbound through the extended outage.
If primary nomination requests through the Mt Vernon CS exceeds the
available capacity of 1,113,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,277,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
Northwest Pipeline apologizes for this extended delay and is
working diligently to safely bring this station back into
service as quickly as possible to minimize any potential
impacts.
This is a superseding post of Notice ID 26-194. Northwest
incorrectly mentioned the Sumas Compressor and that is not
relevant to this maintenance update.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 09/23/2026 11:40 AM MCT
Notice Eff D/T: 09/23/2026 11:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-195
Prior Notice: 26-194
Subject: Mt Vernon Outage Extended Clarification
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is currently performing maintenance at the
Mt. Vernon CS (located at MP 1440.18 in Skagit County,
Washington) from Gas Day September 10, 2026, through Gas Day
September 23, 2026, and referenced in Notice ID 26-173.
However, due to delays on work, this outage has now been
extended through Gas Day September 29, 2026.
The Mt Vernon CS will continue to be limited to 1,113,000 Dth/d
southbound through the extended outage.
If primary nomination requests through the Mt Vernon CS exceeds the
available capacity of 1,113,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,277,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
Northwest Pipeline apologizes for this extended delay and is
working diligently to safely bring this station back into
service as quickly as possible to minimize any potential
impacts.
This is a superseding post of Notice ID 26-194. Northwest
incorrectly mentioned the Sumas Compressor and that is not
relevant to this maintenance update.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 09/23/2026 11:40 AM MCT
Notice Eff D/T: 09/23/2026 11:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-195
Prior Notice: 26-194
Subject: Mt Vernon Outage Extended Clarification
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is currently performing maintenance at the
Mt. Vernon CS (located at MP 1440.18 in Skagit County,
Washington) from Gas Day September 10, 2026, through Gas Day
September 23, 2026, and referenced in Notice ID 26-173.
However, due to delays on work, this outage has now been
extended through Gas Day September 29, 2026.
The Mt Vernon CS will continue to be limited to 1,113,000 Dth/d
southbound through the extended outage.
If primary nomination requests through the Mt Vernon CS exceeds the
available capacity of 1,113,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,277,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
Northwest Pipeline apologizes for this extended delay and is
working diligently to safely bring this station back into
service as quickly as possible to minimize any potential
impacts.
This is a superseding post of Notice ID 26-194. Northwest
incorrectly mentioned the Sumas Compressor and that is not
relevant to this maintenance update.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.