Northwest Notice 26-132
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/02/2026 9:00 AM MCT
Notice Eff D/T: 07/02/2026 9:00 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-132
Prior Notice:
Subject: Muddy Creek ESD, Mosquito Lake, Soda Springs ESD, Mt. Vernon ESD, Pocatello M&ER
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest will be performing maintenance at the
following locations next week:
- Muddy Creek N. Constraint: located at MP 438.62 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Muddy Creek S. Constraint: located at MP 437.56 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Sumas CS: located at MP 1484.48 in Whatcom County,
Washington beginning gas day July 6, 2026, through gas
day July 10, 2026.
- Soda Springs CS: located at MP 528.74 in Bear Lake
County, Idaho beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Mt. Vernon CS: located at MP 1440.18 in Skagit County,
Washington beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Pocatello CS: located at MP 607.28 in Power County, Idaho
beginning gas day July 7, 2026, through gas day July 21,
2026.
The Muddy Creek North Constraint will be limited to 539,000
Dth/d northbound for the duration of the outage.
If primary nomination requests through the Muddy Creek North
Constraint exceeds the available capacity of 539,000 Dth/d
northbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 774,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Muddy Creek South Constraint will be limited to 708,000
Dth/d southbound for the duration of the outage.
If primary nomination requests through the Muddy Creek South
Constraint exceeds the available capacity of 708,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
762,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Sumas CS will be limited to 1,075,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,075,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
The Soda Springs CS will be limited to 570,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Soda Springs CS
exceeds the available capacity of 570,000 Dth/d northbound (or
whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 652,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Mt. Vernon CS will be limited to 1,240,000 Dth/d southbound
for the duration of the outage.
If primary nomination requests through the Mt. Vernon CS
exceeds the available capacity of 1,240,000 Dth/d southbound
(or whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
1,277,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Pocatello CS will be limited to 462,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Pocatello CS exceeds
the available capacity of 462,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 610,000 Dth/d
northbound. The deficiency period will continue until the work
has been completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/02/2026 9:00 AM MCT
Notice Eff D/T: 07/02/2026 9:00 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-132
Prior Notice:
Subject: Muddy Creek ESD, Mosquito Lake, Soda Springs ESD, Mt. Vernon ESD, Pocatello M&ER
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest will be performing maintenance at the
following locations next week:
- Muddy Creek N. Constraint: located at MP 438.62 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Muddy Creek S. Constraint: located at MP 437.56 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Sumas CS: located at MP 1484.48 in Whatcom County,
Washington beginning gas day July 6, 2026, through gas
day July 10, 2026.
- Soda Springs CS: located at MP 528.74 in Bear Lake
County, Idaho beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Mt. Vernon CS: located at MP 1440.18 in Skagit County,
Washington beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Pocatello CS: located at MP 607.28 in Power County, Idaho
beginning gas day July 7, 2026, through gas day July 21,
2026.
The Muddy Creek North Constraint will be limited to 539,000
Dth/d northbound for the duration of the outage.
If primary nomination requests through the Muddy Creek North
Constraint exceeds the available capacity of 539,000 Dth/d
northbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 774,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Muddy Creek South Constraint will be limited to 708,000
Dth/d southbound for the duration of the outage.
If primary nomination requests through the Muddy Creek South
Constraint exceeds the available capacity of 708,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
762,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Sumas CS will be limited to 1,075,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,075,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
The Soda Springs CS will be limited to 570,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Soda Springs CS
exceeds the available capacity of 570,000 Dth/d northbound (or
whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 652,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Mt. Vernon CS will be limited to 1,240,000 Dth/d southbound
for the duration of the outage.
If primary nomination requests through the Mt. Vernon CS
exceeds the available capacity of 1,240,000 Dth/d southbound
(or whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
1,277,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Pocatello CS will be limited to 462,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Pocatello CS exceeds
the available capacity of 462,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 610,000 Dth/d
northbound. The deficiency period will continue until the work
has been completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/02/2026 9:00 AM MCT
Notice Eff D/T: 07/02/2026 9:00 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-132
Prior Notice:
Subject: Muddy Creek ESD, Mosquito Lake, Soda Springs ESD, Mt. Vernon ESD, Pocatello M&ER
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest will be performing maintenance at the
following locations next week:
- Muddy Creek N. Constraint: located at MP 438.62 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Muddy Creek S. Constraint: located at MP 437.56 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Sumas CS: located at MP 1484.48 in Whatcom County,
Washington beginning gas day July 6, 2026, through gas
day July 10, 2026.
- Soda Springs CS: located at MP 528.74 in Bear Lake
County, Idaho beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Mt. Vernon CS: located at MP 1440.18 in Skagit County,
Washington beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Pocatello CS: located at MP 607.28 in Power County, Idaho
beginning gas day July 7, 2026, through gas day July 21,
2026.
The Muddy Creek North Constraint will be limited to 539,000
Dth/d northbound for the duration of the outage.
If primary nomination requests through the Muddy Creek North
Constraint exceeds the available capacity of 539,000 Dth/d
northbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 774,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Muddy Creek South Constraint will be limited to 708,000
Dth/d southbound for the duration of the outage.
If primary nomination requests through the Muddy Creek South
Constraint exceeds the available capacity of 708,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
762,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Sumas CS will be limited to 1,075,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,075,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
The Soda Springs CS will be limited to 570,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Soda Springs CS
exceeds the available capacity of 570,000 Dth/d northbound (or
whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 652,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Mt. Vernon CS will be limited to 1,240,000 Dth/d southbound
for the duration of the outage.
If primary nomination requests through the Mt. Vernon CS
exceeds the available capacity of 1,240,000 Dth/d southbound
(or whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
1,277,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Pocatello CS will be limited to 462,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Pocatello CS exceeds
the available capacity of 462,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 610,000 Dth/d
northbound. The deficiency period will continue until the work
has been completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/02/2026 9:00 AM MCT
Notice Eff D/T: 07/02/2026 9:00 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-132
Prior Notice:
Subject: Muddy Creek ESD, Mosquito Lake, Soda Springs ESD, Mt. Vernon ESD, Pocatello M&ER
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest will be performing maintenance at the
following locations next week:
- Muddy Creek N. Constraint: located at MP 438.62 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Muddy Creek S. Constraint: located at MP 437.56 in
Lincoln County, Wyoming beginning gas day July 6, 2026,
through gas day July 10, 2026.
- Sumas CS: located at MP 1484.48 in Whatcom County,
Washington beginning gas day July 6, 2026, through gas
day July 10, 2026.
- Soda Springs CS: located at MP 528.74 in Bear Lake
County, Idaho beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Mt. Vernon CS: located at MP 1440.18 in Skagit County,
Washington beginning gas day July 7, 2026, through gas
day July 8, 2026.
- Pocatello CS: located at MP 607.28 in Power County, Idaho
beginning gas day July 7, 2026, through gas day July 21,
2026.
The Muddy Creek North Constraint will be limited to 539,000
Dth/d northbound for the duration of the outage.
If primary nomination requests through the Muddy Creek North
Constraint exceeds the available capacity of 539,000 Dth/d
northbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 774,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Muddy Creek South Constraint will be limited to 708,000
Dth/d southbound for the duration of the outage.
If primary nomination requests through the Muddy Creek South
Constraint exceeds the available capacity of 708,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
762,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Sumas CS will be limited to 1,075,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,075,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
The Soda Springs CS will be limited to 570,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Soda Springs CS
exceeds the available capacity of 570,000 Dth/d northbound (or
whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 652,000 Dth/d northbound. The deficiency period
will continue until the work has been completed.
The Mt. Vernon CS will be limited to 1,240,000 Dth/d southbound
for the duration of the outage.
If primary nomination requests through the Mt. Vernon CS
exceeds the available capacity of 1,240,000 Dth/d southbound
(or whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
1,277,000 Dth/d southbound. The deficiency period will continue
until the work has been completed.
The Pocatello CS will be limited to 462,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Pocatello CS exceeds
the available capacity of 462,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 610,000 Dth/d
northbound. The deficiency period will continue until the work
has been completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.