Northwest Notice 26-118
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 06/04/2026 2:07 PM MCT
Notice Eff D/T: 06/04/2026 2:07 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-118
Prior Notice: 26-114
Subject: Caldwell Compressor Station Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-114, Northwest is
currently performing maintenance related to the Highway 20/26
Expansion through the Caldwell compressor station through June
22, 2026.
Primary southbound nomination requests at the Caldwell CS have
exceeded the available capacity of 288,000 Dth/d southbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day June 5, 2026. The Deficiency will be calculated
based on a design capacity of 475,000 Dth/d southbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 06/04/2026 2:07 PM MCT
Notice Eff D/T: 06/04/2026 2:07 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-118
Prior Notice: 26-114
Subject: Caldwell Compressor Station Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-114, Northwest is
currently performing maintenance related to the Highway 20/26
Expansion through the Caldwell compressor station through June
22, 2026.
Primary southbound nomination requests at the Caldwell CS have
exceeded the available capacity of 288,000 Dth/d southbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day June 5, 2026. The Deficiency will be calculated
based on a design capacity of 475,000 Dth/d southbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 06/04/2026 2:07 PM MCT
Notice Eff D/T: 06/04/2026 2:07 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-118
Prior Notice: 26-114
Subject: Caldwell Compressor Station Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-114, Northwest is
currently performing maintenance related to the Highway 20/26
Expansion through the Caldwell compressor station through June
22, 2026.
Primary southbound nomination requests at the Caldwell CS have
exceeded the available capacity of 288,000 Dth/d southbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day June 5, 2026. The Deficiency will be calculated
based on a design capacity of 475,000 Dth/d southbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 06/04/2026 2:07 PM MCT
Notice Eff D/T: 06/04/2026 2:07 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-118
Prior Notice: 26-114
Subject: Caldwell Compressor Station Deficiency Period
Notice Text:
As indicated in All Shippers Notice #26-114, Northwest is
currently performing maintenance related to the Highway 20/26
Expansion through the Caldwell compressor station through June
22, 2026.
Primary southbound nomination requests at the Caldwell CS have
exceeded the available capacity of 288,000 Dth/d southbound (or
whatever Northwest cannot mitigate). Therefore, pursuant to
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for Gas Day June 5, 2026. The Deficiency will be calculated
based on a design capacity of 475,000 Dth/d southbound. The
Deficiency Period will continue until the work is completed.
Northwest will post on its EBB if unable to mitigate volumes
each day until the work is completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.