Northwest Notice 25-078
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 06/05/2025 9:40 AM MCT
Notice Eff D/T: 06/05/2025 9:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-078
Prior Notice:
Subject: Pegram ESD/Lava Solar Inspections, Sumas ESD, & Baker ESD Maintenance Rreminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Pegram CS beginning on gas day June 09, 2025, through gas
day June 13, 2025.
- Sumas CS beginning on gas day June 10, 2025, through gas
day June 11, 2025.
- Baker CS beginning on gas day June 10, 2025, through gas
day June 12, 2025.
The Pegram CS will be limited to 589,000 Dth/d northbound for
the duration of the outage.
If primary nomination requests through the Pegram CS exceeds
the available capacity of 589,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 654,000 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 13, 2025.
The Sumas CS will be limited to 1,070,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,070,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 11, 2025.
The Baker CS will be limited to 357,000 Dth/d northbound and
462,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Baker CS exceeds the
available capacity of 357,000 Dth/d northbound or 462,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
446,000 Dth/d northbound or 491,000 Dth/d southbound. The
deficiency period will continue until the work is completed on
gas day June 12, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 06/05/2025 9:40 AM MCT
Notice Eff D/T: 06/05/2025 9:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-078
Prior Notice:
Subject: Pegram ESD/Lava Solar Inspections, Sumas ESD, & Baker ESD Maintenance Rreminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Pegram CS beginning on gas day June 09, 2025, through gas
day June 13, 2025.
- Sumas CS beginning on gas day June 10, 2025, through gas
day June 11, 2025.
- Baker CS beginning on gas day June 10, 2025, through gas
day June 12, 2025.
The Pegram CS will be limited to 589,000 Dth/d northbound for
the duration of the outage.
If primary nomination requests through the Pegram CS exceeds
the available capacity of 589,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 654,000 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 13, 2025.
The Sumas CS will be limited to 1,070,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,070,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 11, 2025.
The Baker CS will be limited to 357,000 Dth/d northbound and
462,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Baker CS exceeds the
available capacity of 357,000 Dth/d northbound or 462,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
446,000 Dth/d northbound or 491,000 Dth/d southbound. The
deficiency period will continue until the work is completed on
gas day June 12, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 06/05/2025 9:40 AM MCT
Notice Eff D/T: 06/05/2025 9:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-078
Prior Notice:
Subject: Pegram ESD/Lava Solar Inspections, Sumas ESD, & Baker ESD Maintenance Rreminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Pegram CS beginning on gas day June 09, 2025, through gas
day June 13, 2025.
- Sumas CS beginning on gas day June 10, 2025, through gas
day June 11, 2025.
- Baker CS beginning on gas day June 10, 2025, through gas
day June 12, 2025.
The Pegram CS will be limited to 589,000 Dth/d northbound for
the duration of the outage.
If primary nomination requests through the Pegram CS exceeds
the available capacity of 589,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 654,000 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 13, 2025.
The Sumas CS will be limited to 1,070,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,070,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 11, 2025.
The Baker CS will be limited to 357,000 Dth/d northbound and
462,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Baker CS exceeds the
available capacity of 357,000 Dth/d northbound or 462,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
446,000 Dth/d northbound or 491,000 Dth/d southbound. The
deficiency period will continue until the work is completed on
gas day June 12, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 06/05/2025 9:40 AM MCT
Notice Eff D/T: 06/05/2025 9:40 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-078
Prior Notice:
Subject: Pegram ESD/Lava Solar Inspections, Sumas ESD, & Baker ESD Maintenance Rreminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Pegram CS beginning on gas day June 09, 2025, through gas
day June 13, 2025.
- Sumas CS beginning on gas day June 10, 2025, through gas
day June 11, 2025.
- Baker CS beginning on gas day June 10, 2025, through gas
day June 12, 2025.
The Pegram CS will be limited to 589,000 Dth/d northbound for
the duration of the outage.
If primary nomination requests through the Pegram CS exceeds
the available capacity of 589,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 654,000 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 13, 2025.
The Sumas CS will be limited to 1,070,000 Dth/d southbound for
the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the
available capacity of 1,070,000 Dth/d southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 1,409,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 11, 2025.
The Baker CS will be limited to 357,000 Dth/d northbound and
462,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Baker CS exceeds the
available capacity of 357,000 Dth/d northbound or 462,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
446,000 Dth/d northbound or 491,000 Dth/d southbound. The
deficiency period will continue until the work is completed on
gas day June 12, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.