Northwest Notice 25-076
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 05/29/2025 10:26 AM MCT
Notice Eff D/T: 05/29/2025 10:26 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-076
Prior Notice:
Subject: Kemmerer ESD & Caldwell ESD - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Kemmerer CS on gas day June 02, 2025.
- Caldwell CS beginning gas day June 03, 2025, through
gas day June 05, 2025.
The Kemmerer CS will be limited to 729,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Kemmerer CS exceeds
the available capacity of 729,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 772,925 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 02, 2025.
The Caldwell CS will be limited to 404,000 Dth/d northbound and
438,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Caldwell CS exceeds
the available capacity of 404,000 Dth/d northbound or 438,000
Dth/d southbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 452,000 Dth/d northbound or 475,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 05, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 05/29/2025 10:26 AM MCT
Notice Eff D/T: 05/29/2025 10:26 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-076
Prior Notice:
Subject: Kemmerer ESD & Caldwell ESD - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Kemmerer CS on gas day June 02, 2025.
- Caldwell CS beginning gas day June 03, 2025, through
gas day June 05, 2025.
The Kemmerer CS will be limited to 729,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Kemmerer CS exceeds
the available capacity of 729,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 772,925 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 02, 2025.
The Caldwell CS will be limited to 404,000 Dth/d northbound and
438,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Caldwell CS exceeds
the available capacity of 404,000 Dth/d northbound or 438,000
Dth/d southbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 452,000 Dth/d northbound or 475,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 05, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 05/29/2025 10:26 AM MCT
Notice Eff D/T: 05/29/2025 10:26 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-076
Prior Notice:
Subject: Kemmerer ESD & Caldwell ESD - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Kemmerer CS on gas day June 02, 2025.
- Caldwell CS beginning gas day June 03, 2025, through
gas day June 05, 2025.
The Kemmerer CS will be limited to 729,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Kemmerer CS exceeds
the available capacity of 729,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 772,925 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 02, 2025.
The Caldwell CS will be limited to 404,000 Dth/d northbound and
438,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Caldwell CS exceeds
the available capacity of 404,000 Dth/d northbound or 438,000
Dth/d southbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 452,000 Dth/d northbound or 475,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 05, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 05/29/2025 10:26 AM MCT
Notice Eff D/T: 05/29/2025 10:26 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-076
Prior Notice:
Subject: Kemmerer ESD & Caldwell ESD - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing maintenance at the following
locations:
- Kemmerer CS on gas day June 02, 2025.
- Caldwell CS beginning gas day June 03, 2025, through
gas day June 05, 2025.
The Kemmerer CS will be limited to 729,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Kemmerer CS exceeds
the available capacity of 729,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 772,925 Dth/d
northbound. The deficiency period will continue until the work
is completed on gas day June 02, 2025.
The Caldwell CS will be limited to 404,000 Dth/d northbound and
438,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Caldwell CS exceeds
the available capacity of 404,000 Dth/d northbound or 438,000
Dth/d southbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 452,000 Dth/d northbound or 475,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on gas day June 05, 2025.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.