Northern Border Pipeline Company Notice 25992320
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TSP Name
Northern Border Pipeline Company
TSP
021632583
Date
Time
Notice ID
25992320
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
04/23/26
04/23/26
10/31/26
9:21:53 AM
12:00:00 AM
12:00:00 AM
Subject: Construction and Maintenance Schedule - Updated (April 23, 2026)
Author: Mark Begley
Notice Text
As a courtesy, Northern Border Pipeline (NBPL) hereby notifies customers of the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website. NBPL reminds customers to please check the Maintenance Schedule on a regular basis.Changes since last posting:· Date Change- Zeeland Station 8 Spring Outage and Borescope from original date of 4/24 to new date 4/27· Add – Glen Ullin Station 6 Bison XP ESD testing on 4/24· Remove – St Anthony Station 7 Regulator and Reliefs Inspection on 4/25· Date Change – Manning Station 5 Bison XP ESD Testing - from original dates of 4/28 through 4/30 to new date of 4/29 (duration and impact reduction)
Additionally, the following file(s) can be located on Informational Postings under Construction and Maintenance
2026 NBPL maintenance schedule 042326.pdf
Northern Border Pipeline Company
TSP
021632583
Date
Time
Notice ID
25992320
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
04/23/26
04/23/26
10/31/26
9:21:53 AM
12:00:00 AM
12:00:00 AM
Subject: Construction and Maintenance Schedule - Updated (April 23, 2026)
Author: Mark Begley
Notice Text
As a courtesy, Northern Border Pipeline (NBPL) hereby notifies customers of the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website. NBPL reminds customers to please check the Maintenance Schedule on a regular basis.Changes since last posting:· Date Change- Zeeland Station 8 Spring Outage and Borescope from original date of 4/24 to new date 4/27· Add – Glen Ullin Station 6 Bison XP ESD testing on 4/24· Remove – St Anthony Station 7 Regulator and Reliefs Inspection on 4/25· Date Change – Manning Station 5 Bison XP ESD Testing - from original dates of 4/28 through 4/30 to new date of 4/29 (duration and impact reduction)
Additionally, the following file(s) can be located on Informational Postings under Construction and Maintenance
2026 NBPL maintenance schedule 042326.pdf