| FORCE MAJ/STORAGE | 11/13/25 | 11/14/25 | 12/31/00 | 37651 | 2 | UPDATE - CLAY BASIN FORCE MAJEURE COMPLETED | |
| PIPE COND/CONSTRAINT | 11/11/25 | 11/11/25 | 12/31/00 | 37631 | 2 | SKULL CREEK DELIVERIES TO SOUTHERN STAR MAP 167 | |
| CONSTRAINT | 11/10/25 | 11/10/25 | 12/31/00 | 37612 | 1 | SKULL CREEK DELIVERIES TO SOUTHERN STAR MAP 167 | |
| STORAGE | 11/10/25 | 11/10/25 | 12/31/00 | 37611 | 1 | CLAY BASIN CAPACITIES | |
| STORAGE | 11/04/25 | 11/05/25 | 12/31/00 | 37591 | 1 | CLAY BASIN CAPACITIES | |
| STORAGE | 10/30/25 | 11/01/25 | 12/31/00 | 37570 | 1 | CLAY BASIN ISS CAPACITY. | |
| STORAGE | 10/28/25 | 10/29/25 | 12/31/00 | 37530 | 1 | CLAY BASIN CAPACITIES | |
| STORAGE | 10/27/25 | 10/27/25 | 12/31/00 | 37510 | 1 | CLAY BASIN ISS INJECTION/TRANSFERS | |
| STORAGE | 10/23/25 | 10/24/25 | 12/31/00 | 37474 | 1 | CLAY BASIN CAPACITIES | |
| STORAGE | 10/15/25 | 10/16/25 | 12/31/00 | 37430 | 1 | CLAY BASIN CAPACITIES | |
| CONSTRAINT/MAINT | 09/25/25 | 09/25/25 | 12/31/00 | 37333 | 2 | SUPERSEDE: ML23 LINE LOWERING | |
| STORAGE | 09/03/25 | 09/04/25 | 12/31/00 | 37190 | 1 | CLAY BASIN CAPACITIES | |
| STORAGE/OFO/PLND OUTAGE | 09/02/25 | 09/16/25 | 10/15/25 | 37170 | 1 | 2025 CLAY BASIN FALL INJECTION TEST | |
| STORAGE | 08/26/25 | 08/27/25 | 12/31/00 | 37090 | 1 | CRITICAL, STORAGE CLAY BASIN CAPACITIES | |
| CONSTRAINT | 08/25/25 | 09/09/25 | 09/26/25 | 37071 | 1 | ML122 TAP AND LATERAL INSTALL | |
| FORCE MAJ | 08/22/25 | 08/22/25 | 12/31/00 | 37050 | 2 | WHITE RIVER HUB MAP 409 RECEIPT | |
| MAINT/CONSTRAINT | 08/21/25 | 08/21/25 | 12/31/00 | 37032 | 2 | SUPERSEDE: WHITNEY CANYON BATTERY CHARGER REPLACEMENT | |
| MAINT/CONSTRAINT | 08/20/25 | 08/20/25 | 12/31/00 | 37031 | 2 | SUPERSEDE: LINEBREAK VALVE CROSSOVER 16 BATTERY CHARGER REPLACEMENT | |
| CONSTRAINT/MAINT | 08/13/25 | 09/15/25 | 09/27/25 | 36991 | 1 | ML23 LINE LOWERING | |
| MAINT/CONSTRAINT | 07/25/25 | 08/21/25 | 12/31/00 | 36910 | 1 | WHITNEY CANYON BATTERY CHARGER REPLACEMENT | |
| MAINT/CONSTRAINT | 07/24/25 | 08/20/25 | 12/31/00 | 36909 | 1 | LINEBREAK VALVE CROSSOVER 16 BATTERY CHARGER REPLACEMENT | |
| OTHER | 05/01/14 | 05/01/14 | 12/31/00 | 15967 | 1 | NOTICE OF PERIODIC PURCHASES AND SALES OF NATURAL GAS |