Type Posted Effective End Identifier Status Subject Response
FORCE MAJ/STORAGE 06/12/25 06/12/25 12/31/00 36687 2 UPDATE - CLAY BASIN FORCE MAJEURE
FORCE MAJ/CONSTRAINT 06/06/25 06/06/25 12/31/00 36646 1 FORCE MAJEURE - CLAY BASIN INJECTION CAPACITY
STORAGE 06/03/25 06/05/25 12/31/00 36626 1 CLAY BASIN CAPACITIES
MAINT/CONSTRAINT 05/22/25 05/22/25 12/31/00 36586 2 THISTLE CREEK COMPRESSOR STATION UNIT 1 ENGINE EXCHANGE
MAINT/CONSTRAINT 05/14/25 06/09/25 06/11/25 36513 1 LINEBREAK VALVE CROSSOVER 16 CONSTRUCTION
MAINT/CONSTRAINT 05/13/25 05/20/25 05/23/25 36509 1 THISTLE CREEK COMPRESSOR STATION UNIT 1 ENGINE EXCHANGE
STORAGE 05/13/25 05/15/25 12/31/00 36507 1 CLAY BASIN CAPACITIES
MAINT/CONSTRAINT 05/13/25 05/14/25 05/15/25 36506 2 REVISED: KANDA COMPRESSOR STATION ANNUAL EMERGENCY SHUTDOWN (ESD) AND UNIT MAINTENANCE
MAINT/CONSTRAINT 05/07/25 05/15/25 05/16/25 36466 1 KANDA COMPRESSOR STATION ANNUAL EMERGENCY SHUTDOWN (ESD) AND UNIT MAINTENANCE
CONSTRAINT 04/09/25 05/07/25 07/25/25 36326 1 LEROY COMPRESSOR STATION ENGINE EXCHANGE
CONSTRAINT 04/07/25 04/15/25 04/17/25 36286 1 CRITICAL, PLND OUTAGE/MAINT/CONSTRAINT, 20250407, MWP, 092027077-->OAK SPRING C S MAINTENANCE AND ANNUAL ESD
STORAGE 03/27/25 04/10/25 12/31/00 36266 1 CLAY BASIN CAPACITIES AND OFO RESTRICTIONS
STORAGE/OFO/PLND OUTAGE 03/05/25 03/13/25 04/10/25 36106 1 2025 ANNUAL CLAY BASIN WITHDRAWAL TEST
OTHER 05/01/14 05/01/14 12/31/00 15967 1 NOTICE OF PERIODIC PURCHASES AND SALES OF NATURAL GAS