Type | Posted | Effective | End | Identifier | Status | Subject | Response |
---|---|---|---|---|---|---|---|
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 06/12/25 | 06/24/25 | 06/25/25 | 123999 | H-600 Pipeline Pigging (Mobley Run IC to Bradshaw CS) 06-24-25 Update 3 | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 06/12/25 | 07/14/25 | 07/18/25 | 123959 | H-600 Pipeline Pig Run (Stallworth CS to Cherrystone IC) 07-14-25 | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 05/29/25 | 05/29/25 | 06/05/25 | 123499 | H-600 Pipeline Pig Run (Bradshaw CS to Harris CS) 05-27-25 Complete | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 05/06/25 | 05/27/25 | 05/30/25 | 122739 | H-600 Pipeline Pig Run (Bradshaw CS to Harris CS) 05-27-25 Update | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 05/01/25 | 06/17/25 | 06/18/25 | 122579 | H-600 Pipeline Pigging and Harris Compressor Station Maintenance 06-17-25 Update 2 | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/23/25 | 04/23/25 | 05/04/25 | 122240 | H-600 Pipeline Pigging and Harris Compressor Station Maintenance 05-06-25 Update | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/21/25 | 05/27/25 | 05/30/25 | 122159 | H-600 Pipeline Pig Run (Bradshaw CS to Harris CS) 05-27-25 | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/11/25 | 04/11/25 | 04/12/25 | 121879 | Stallworth and Bradshaw Compressor Station Maintenance 04-08-25 Complete | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/09/25 | 04/09/25 | 07/31/25 | 121779 | Stallworth and Bradshaw Compressor Station Maintenance 04-08-25 Update | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/04/25 | 04/04/25 | 04/05/25 | 121639 | Stallworth Compressor Station Maintenance 04-01-25 Complete | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 04/01/25 | 05/06/25 | 05/09/25 | 121459 | H-600 Pipeline Pigging and Harris Compressor Station Maintenance 05-06-25 | ||
CAPACITY CONSTRAINT | 03/27/25 | 03/27/25 | 06/30/25 | 121261 | Equitrans to MVP Capacity Constraint Update 07-25-24 | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 02/18/25 | 04/08/25 | 04/10/25 | 119979 | Stallworth and Bradshaw Compressor Station Maintenance 04-08-25 | ||
PLANNED SERVICE OUTAGE/CAPACITY CONSTRAINT | 02/18/25 | 04/01/25 | 04/03/25 | 119959 | Stallworth Compressor Station Maintenance 04-01-25 | ||
CAPACITY CONSTRAINT | 01/10/25 | 01/10/25 | 04/30/25 | 118859 | Cherrystone IC Unplanned Outage 01-10-25 Complete | ||
CAPACITY CONSTRAINT | 01/09/25 | 01/09/25 | 04/30/25 | 118820 | Cherrystone IC Unplanned Outage 01-10-25 |