Type Posted Effective End Identifier Status Subject Response
Capacity Constraint 04/18/25 04/18/25 07/18/25 1717 MSPL – MS100011-CHISHOLM-R Location Off Rate – LIFTED Effective April 18, 2025
Capacity Constraint 04/11/25 04/11/25 07/11/25 1712 MSPL – MS100011-CHISHOLM-R Location Off Rate Effective April 11, 2025
Capacity Constraint 03/29/25 03/29/25 06/29/25 1698 MSPL – MS101521-CANA-R Location Off Rate – LIFTED Effective March 29, 2025
Planned Service Outage 02/03/25 02/03/25 06/30/25 1628 MSPL 2025 Planned Outage and Maintenance Summary – 02.03.25