Keystone Gas Storage Notice 122623
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 89891472-KM KEYSTONE GAS STORAGE | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 09/15/2025 1:59:32PM | Notice End Date/Time: 09/16/2025 9:00:00am |
Post Date/Time: 9/15/2025 1:59:32 PM | Notice ID: 122623 |
Reqrd Rsp: 1 | Rsp Date: 09/15/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: Operations Planning Report October 2025 |
Kinder Morgan Keystone Gas Storage LLC |
||||||||||
Operations Planning Report October 2025 |
||||||||||
Issued September 15, 2025 |
||||||||||
Pipe |
Start Date |
End Date |
County, ST |
Scheduling Location |
Maintenance List |
Base Capacity (Dth) |
Reduction (Dth) |
Net (Dth) |
Flow Indication |
Update |
10/1/25 |
10/1/25 |
WINKLER, TX |
INJECTION |
Keystone Station maintenance |
91,800 |
91,800 |
0 |
Injection |
||
KGS |
10/1/25 |
10/1/25 |
WINKLER, TX |
INJECTION |
Keystone Station maintenance |
91,800 |
34,425 |
Cycle
4 |
Injection |
|
KGS |
10/1/25 |
10/1/25 |
WINKLER, TX |
WITHDRAWAL |
Keystone Station maintenance |
367,200 |
367,200 |
0 |
Withdrawal |
|
KGS |
10/1/25 |
10/1/25 |
WINKLER, TX |
WITHDRAWAL |
Keystone Station maintenance |
367,200 |
137,700 |
Cycle
4 |
Withdrawal |
|
KGS |
10/20/25 |
10/24/25 |
WINKLER, TX |
INJECTION |
Unit 4 Inspection |
91,800 |
45,900 |
45,900 |
Injection |
TSP/TSP Name: 89891472-KM KEYSTONE GAS STORAGE | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 09/15/2025 1:59:32PM | Notice End Date/Time: 09/16/2025 9:00:00am |
Post Date/Time: 9/15/2025 1:59:32 PM | Notice ID: 122623 |
Reqrd Rsp: 1 | Rsp Date: 09/15/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: Operations Planning Report October 2025 |
Kinder Morgan Keystone Gas Storage LLC |
||||||||||
Operations Planning Report October 2025 |
||||||||||
Issued September 15, 2025 |
||||||||||
Pipe |
Start Date |
End Date |
County, ST |
Scheduling Location |
Maintenance List |
Base Capacity (Dth) |
Reduction (Dth) |
Net (Dth) |
Flow Indication |
Update |
10/1/25 |
10/1/25 |
WINKLER, TX |
INJECTION |
Keystone Station maintenance |
91,800 |
91,800 |
0 |
Injection |
||
KGS |
10/1/25 |
10/1/25 |
WINKLER, TX |
INJECTION |
Keystone Station maintenance |
91,800 |
34,425 |
Cycle
4 |
Injection |
|
KGS |
10/1/25 |
10/1/25 |
WINKLER, TX |
WITHDRAWAL |
Keystone Station maintenance |
367,200 |
367,200 |
0 |
Withdrawal |
|
KGS |
10/1/25 |
10/1/25 |
WINKLER, TX |
WITHDRAWAL |
Keystone Station maintenance |
367,200 |
137,700 |
Cycle
4 |
Withdrawal |
|
KGS |
10/20/25 |
10/24/25 |
WINKLER, TX |
INJECTION |
Unit 4 Inspection |
91,800 |
45,900 |
45,900 |
Injection |