Guardian Pipeline Notice 1742

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name: Guardian Pipeline, L.L.C.

TSP: 03-175-2897

Subject: COMPLETE: Planned Service Outage - Joliet Station

Notice Type: Constraint

Critical: Yes

Post Date/Time:: 09/12/2025 08:10 am

Notice Eff Date/Time: 09/08/2025 09:00 am

NOTICE_END_DATE: 09/13/2025 09:00 am

Notice ID: 1742

Notice Stat Desc: Supersede

Prior Notice: 1733

Reqrd Rsp Desc: No response required

Rsp Date/Time:

Notice Text:

The planned maintenance at the Joliet Station is now complete.

The Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity will be reinstated effective Gas Day, Saturday, September 13, 2025, Timely Cycle.

Please contact your Commercial representative with questions.

-------------------------------------------------------------------------
Prior Notice ID: 1733

The planned maintenance at the Joliet Station has been amended.

Guardian Pipeline, L.L.C, (GPL) will decrease Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity beginning Gas Day Wednesday, September 10, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day Friday, September 12, 2025.

Joliet ANR receipt capacity will be reduced from 1,586,820 Dth to 0 Dth.
Joliet Vector receipt and delivery capacity will be reduced from 1,005,940 Dth to 0 Dth.
Joliet Alliance receipt capacity will be reduced from 1,390,720 Dth to 0 Dth.
Joliet Peoples delivery capacity will be reduced from 196,100 Dth to 0 Dth.

Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.

GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with questions.

------------------------------------------------------------------------

Prior Notice ID: 1733

Due to planned maintenance at the Joliet Station, Guardian Pipeline, L.L.C, (GPL) will decrease Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity beginning Gas Day Monday, September 08, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day Tuesday, September 9, 2025.

Joliet ANR receipt capacity will be reduced from 1,586,820 Dth to 0 Dth.
Joliet Vector receipt and delivery capacity will be reduced from 1,005,940 Dth to 0 Dth.
Joliet Alliance receipt capacity will be reduced from 1,390,720 Dth to 0 Dth.
Joliet Peoples delivery capacity will be reduced from 196,100 Dth to 0 Dth.

Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.

GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with questions.
TSP Name: Guardian Pipeline, L.L.C.

TSP: 03-175-2897

Subject: COMPLETE: Planned Service Outage - Joliet Station

Notice Type: Constraint

Critical: Yes

Post Date/Time:: 09/12/2025 08:10 am

Notice Eff Date/Time: 09/08/2025 09:00 am

NOTICE_END_DATE: 09/13/2025 09:00 am

Notice ID: 1742

Notice Stat Desc: Supersede

Prior Notice: 1733

Reqrd Rsp Desc: No response required

Rsp Date/Time:

Notice Text:

The planned maintenance at the Joliet Station is now complete.

The Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity will be reinstated effective Gas Day, Saturday, September 13, 2025, Timely Cycle.

Please contact your Commercial representative with questions.

-------------------------------------------------------------------------
Prior Notice ID: 1733

The planned maintenance at the Joliet Station has been amended.

Guardian Pipeline, L.L.C, (GPL) will decrease Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity beginning Gas Day Wednesday, September 10, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day Friday, September 12, 2025.

Joliet ANR receipt capacity will be reduced from 1,586,820 Dth to 0 Dth.
Joliet Vector receipt and delivery capacity will be reduced from 1,005,940 Dth to 0 Dth.
Joliet Alliance receipt capacity will be reduced from 1,390,720 Dth to 0 Dth.
Joliet Peoples delivery capacity will be reduced from 196,100 Dth to 0 Dth.

Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.

GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with questions.

------------------------------------------------------------------------

Prior Notice ID: 1733

Due to planned maintenance at the Joliet Station, Guardian Pipeline, L.L.C, (GPL) will decrease Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity beginning Gas Day Monday, September 08, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day Tuesday, September 9, 2025.

Joliet ANR receipt capacity will be reduced from 1,586,820 Dth to 0 Dth.
Joliet Vector receipt and delivery capacity will be reduced from 1,005,940 Dth to 0 Dth.
Joliet Alliance receipt capacity will be reduced from 1,390,720 Dth to 0 Dth.
Joliet Peoples delivery capacity will be reduced from 196,100 Dth to 0 Dth.

Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.

GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with questions.