Great Lakes Gas Transmission Notice 1201
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name
Notice ID
TSP
Notice Eff Date:
Posting Date/Time:
Notice End Date:
Critical:
Notice Eff Time:
Notice Type:
Notice End Time:
Notice Status:
Required Response:
Prior Notice ID:
Response Date/Time:
Subject
Message Text
Great Lakes Gas Transmission Maintenance Schedule has been updated.
Please refer to the maintenance schedule for the projected capacity impacts. Updated items are as follows:
• Add – GLGT dig program dates
• Date Change – Farwell Station 12 HP Replacement and TSA Automation Upgrade was changed from original dates of 7/28 through 9/30 to new dates of 9/22 through 10/21
• Date Change – Naubinway Station 10 HP Replacement and TSA Automation Upgrade was changed from original dates of 10/6 through 11/16 to new dates of 9/23 through 10/30 and 11/17 through 11/19
• Add – Crystal Falls Station 8 New HP Installation Project on 8/4 through 8/7
• Add – Sta 8 to Sta 9 EMAT Tool Run (100-line) on 8/14
• Date Change – Crystal Falls Station 8 New HP Installation Project from original dates of 10/1 through 10/5 to new dates of 9/1 through 9/4
• Add – Iron River Station 6 A-line valve replacement on 9/29 through 10/5
Please note that the information posted is proposed and subject to change.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 866-454-7572.
TSP Name
Notice ID
TSP
Notice Eff Date:
Posting Date/Time:
Notice End Date:
Critical:
Notice Eff Time:
Notice Type:
Notice End Time:
Notice Status:
Required Response:
Prior Notice ID:
Response Date/Time:
Subject
Message Text
Great Lakes Gas Transmission Maintenance Schedule has been updated.
Please refer to the maintenance schedule for the projected capacity impacts. Updated items are as follows:
• Add – GLGT dig program dates
• Date Change – Farwell Station 12 HP Replacement and TSA Automation Upgrade was changed from original dates of 7/28 through 9/30 to new dates of 9/22 through 10/21
• Date Change – Naubinway Station 10 HP Replacement and TSA Automation Upgrade was changed from original dates of 10/6 through 11/16 to new dates of 9/23 through 10/30 and 11/17 through 11/19
• Add – Crystal Falls Station 8 New HP Installation Project on 8/4 through 8/7
• Add – Sta 8 to Sta 9 EMAT Tool Run (100-line) on 8/14
• Date Change – Crystal Falls Station 8 New HP Installation Project from original dates of 10/1 through 10/5 to new dates of 9/1 through 9/4
• Add – Iron River Station 6 A-line valve replacement on 9/29 through 10/5
Please note that the information posted is proposed and subject to change.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 866-454-7572.