Due to downstream operational constraints, Golden Pass Pipeline (GPPL) is unable to deliver gas
quantities to Florida Gas Transmission (meter 746935). Effective Gas Day Friday (7/19/2024) and
until further notice, GPPL will reduce its Operational Capacity to 0.
GPPL will continue to monitor this delivery point and provide an update if operational conditions
change.
Meter
Delivery Meter
Capacity
Duration
FGT
746935
0
Unit Further Notice
Please contact Kathy Medrano at 713-860.6330 should you have any questions.
Due to downstream operational constraints, Golden Pass Pipeline (GPPL) is unable to deliver gas
quantities to Florida Gas Transmission (meter 746935). Effective Gas Day Friday (7/19/2024) and
until further notice, GPPL will reduce its Operational Capacity to 0.
GPPL will continue to monitor this delivery point and provide an update if operational conditions