Gas Transmission Northwest Notice 1584

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name

Gas Transmission Northwest LLC

Notice ID

1584

TSP

006912885

Notice Eff Date:

06/17/2026

Posting Date/Time:

06/17/2026 16:15

Notice End Date:

06/23/2026

Critical:

Yes

Notice Eff Time:

16:15

Notice Type:

Maint

Notice End Time:

08:59

Notice Status:

Supersede

Required Response:

No response required

Prior Notice ID:

1580

Response Date/Time:

Subject

UPDATED: CAPACITY REDUCTION: GTN – Station 9 CFTP (Updated: 6/17/26)

Message Text

Since the last posting, GTN has extended the A Iine Ione to Bend ILI maintenance through 6/22 (previously 6/17) and updated the capacity impact at Station 9 CFTP (LOC #18480). As a result, capacity will be reduced as follows:

6/9 – 6/18 – Available Capacity 1,800 MMcf/d

6/19 – 6/22 - Available Capacity 1,650 MMcf/d

Please refer to the EBB for any additional capacity impacts.

GTN anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. The Reservation Charge Crediting Mechanism of Section 5.1.3.10 shall apply to this outage.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 888-750-6275. 

TSP Name

Gas Transmission Northwest LLC

Notice ID

1584

TSP

006912885

Notice Eff Date:

06/17/2026

Posting Date/Time:

06/17/2026 16:15

Notice End Date:

06/23/2026

Critical:

Yes

Notice Eff Time:

16:15

Notice Type:

Maint

Notice End Time:

08:59

Notice Status:

Supersede

Required Response:

No response required

Prior Notice ID:

1580

Response Date/Time:

Subject

UPDATED: CAPACITY REDUCTION: GTN – Station 9 CFTP (Updated: 6/17/26)

Message Text

Since the last posting, GTN has extended the A Iine Ione to Bend ILI maintenance through 6/22 (previously 6/17) and updated the capacity impact at Station 9 CFTP (LOC #18480). As a result, capacity will be reduced as follows:

6/9 – 6/18 – Available Capacity 1,800 MMcf/d

6/19 – 6/22 - Available Capacity 1,650 MMcf/d

Please refer to the EBB for any additional capacity impacts.

GTN anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. The Reservation Charge Crediting Mechanism of Section 5.1.3.10 shall apply to this outage.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 888-750-6275.