TSP Name: Empire Pipeline, Inc. - Critical Notice
TSP: 609775049
Post Date: 5/4/2026
Post Time: 09:24:00AM CCT
Notice Type: Maintenance, Pipeline Conditions
Reqrd Rsp: 5
Critical: Y
Notice ID: 1251114
Notice Status: 1
Notice Eff Date/Time: 5/20/2026 07:00:00AM CCT
Notice End Date/Time: 5/21/2026 09:00:00AM CCT
Superseded System Notice ID:
Subject: Jackson ESD Testing - May 2026
Notice Text
Jackson ESD Testing - May 2026
Jackson compressor station will undergo ESD testing for several hours on 5/20.
Upstream operators may experience high pressure and fluctuations in flow during this testing.
Updates will be provided as available.
TSP Name: Empire Pipeline, Inc. - Critical Notice
TSP: 609775049
Post Date: 5/4/2026
Post Time: 09:24:00AM CCT
Notice Type: Maintenance, Pipeline Conditions
Reqrd Rsp: 5
Critical: Y
Notice ID: 1251114
Notice Status: 1
Notice Eff Date/Time: 5/20/2026 07:00:00AM CCT
Notice End Date/Time: 5/21/2026 09:00:00AM CCT
Superseded System Notice ID:
Subject: Jackson ESD Testing - May 2026
Notice Text
Jackson ESD Testing - May 2026
Jackson compressor station will undergo ESD testing for several hours on 5/20.
Upstream operators may experience high pressure and fluctuations in flow during this testing.
Updates will be provided as available.