Eastern Gas Transmission and Storage Critical Notices
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Type | Posted | Effective | End | Identifier | Status | Subject | Response |
---|---|---|---|---|---|---|---|
Maintenance | 09/16/25 | 09/17/25 | 1007873 | Hastings Extraction Plant Unplanned Maintenance | |||
Maintenance | 09/16/25 | 09/16/25 | 1007871 | Hastings Extraction Plant Operations | |||
Capacity Constraint | 09/15/25 | 09/15/25 | 1007857 | Limited Daily and Hourly Flexibility: Manage Receipts and Deliveries | |||
Maintenance | 09/09/25 | 09/09/25 | 1007752 | Pipeline TL-265 Returned to Service | |||
Maintenance | 09/08/25 | 09/08/25 | 1007745 | Pipeline TL-265 Unplanned Maintenance | |||
Capacity Constraint | 09/02/25 | 09/02/25 | 1007655 | Limited Daily and Hourly Flexibility: Manage Receipts and Deliveries | |||
Capacity Constraint | 08/28/25 | 08/28/25 | 1007595 | LN-19 & LN-20 Receipt Capacity Constraint | |||
Scheduling Alert | 08/28/25 | 08/28/25 | 1007589 | System Alert – Transportation Due Shipper Imbalances | |||
Capacity Constraint | 08/22/25 | 08/26/25 | 1007508 | LN-19 & LN-20 Receipt Capacity Constraint | |||
Capacity Constraint | 08/21/25 | 08/21/25 | 1007487 | LN-19 & LN-20 Receipt Capacity Constraint | |||
Maintenance | 08/20/25 | 08/20/25 | 1007470 | Pipeline TL-360 Returned to Service | |||
Capacity Constraint | 08/19/25 | 08/20/25 | 1007463 | NIMO East and Bethlehem Energy Center Restrictions Terminated | |||
Capacity Constraint | 08/15/25 | 08/15/25 | 1007286 | Limited Daily and Hourly Flexibility: Manage Receipts and Deliveries | |||
Maintenance | 08/15/25 | 08/15/25 | 1007406 | Pipeline TL-360 Unplanned Maintenance | |||
Capacity Constraint | 08/12/25 | 08/12/25 | 1007365 | LN-19 & LN-20 Receipt Capacity Constraint | |||
Capacity Constraint | 08/06/25 | 08/06/25 | 1007284 | NIMO East and BEC Restrictions Remain in Effect | |||
Capacity Constraint | 08/05/25 | 08/05/25 | 1007274 | Limited Daily and Hourly Flexibility: Manage Receipts and Deliveries | |||
Scheduling Alert | 08/04/25 | 08/04/25 | 1007248 | Intra Cycle Setpoint Change Requests | |||
Operational Alert | 08/04/25 | 08/05/25 | 1007247 | OFO Advisory: PL-1 FTNN Remains in Effect | |||
Computer System Status | 08/01/25 | 08/01/25 | 1007208 | Dekaflow Intermittent Issues Resolved | |||
Capacity Constraint | 08/01/25 | 08/01/25 | 1007207 | Clarington Capacity Restriction Termination | |||
Computer System Status | 08/01/25 | 08/01/25 | 1007203 | Dekaflow System Experiencing Intermittent Issues | |||
Capacity Constraint | 07/28/25 | 07/28/25 | 1007133 | TL-400 Restrictions Update | |||
Capacity Constraint | 07/25/25 | 07/25/25 | 1007090 | TL-400 Extension Restriction Termination | |||
Capacity Constraint | 07/21/25 | 07/21/25 | 1007031 | TL-400 Restriction | |||
Maintenance | 07/18/25 | 07/18/25 | 1006992 | Pipeline TL-342 Returned to Service | |||
Maintenance | 07/17/25 | 07/17/25 | 1006973 | Pipeline TL-342 Unplanned Maintenance | |||
Capacity Constraint | 07/16/25 | 07/21/25 | 1006960 | Clarington Capacity Restriction - Revised | |||
Capacity Constraint | 07/16/25 | 07/20/25 | 1006958 | TL-400 Ext. Receipt Capacity Restriction - Revised | |||
Capacity Constraint | 07/16/25 | 07/21/25 | 1006957 | Clarington Capacity Restriction | |||
Capacity Constraint | 07/16/25 | 07/20/25 | 1006956 | TL-400 Receipt Capacity Restriction | |||
Capacity Constraint | 07/16/25 | 07/20/25 | 1006954 | TL-400 Ext. Receipt Capacity Restriction | |||
Capacity Constraint | 07/16/25 | 07/20/25 | 1006953 | NIMO East and Bethlehem Energy Center Restrictions | |||
Capacity Constraint | 07/16/25 | 07/16/25 | 1006952 | Limited Daily and Hourly Flexibility: Manage Receipts and Deliveries | |||
Capacity Constraint | 07/10/25 | 07/10/25 | 1006859 | LN-19 & LN-20 Receipt Capacity Constraint | |||
Maintenance | 07/09/25 | 07/09/25 | 1006846 | Quantico Compressor Station Unit #1 Returned to Service | |||
Maintenance | 07/08/25 | 07/09/25 | 1006829 | LN-19 & LN-20 Receipt Capacity Constraint | |||
Maintenance | 07/07/25 | 07/07/25 | 1006809 | Quantico Compressor Station Unit #1 Unplanned Maintenance | |||
Capacity Constraint | 07/01/25 | 07/01/25 | 1006702 | Limited Daily and Hourly Flexibility: Manage Receipts and Deliveries | |||
Maintenance | 07/01/25 | 07/01/25 | 1006701 | Lightburn Unit #6 Returned to Service | |||
Capacity Constraint | 07/01/25 | 07/01/25 | 1006698 | PL-1 Restrictions Termination | |||
Capacity Constraint | 06/25/25 | 06/25/25 | 1006606 | TL-360 Receipt Capacity Restriction Lifted | |||
Capacity Constraint | 06/19/25 | 06/22/25 | 1006526 | PL-1 Restrictions | |||
Capacity Constraint | 06/16/25 | 06/16/25 | 1006488 | Limited Daily and Hourly Flexibility: Manage Receipts and Deliveries | |||
Capacity Constraint | 06/10/25 | 06/13/25 | 1006398 | TL-360 Receipt Capacity Restriction | |||
Capacity Constraint | 05/30/25 | 05/30/25 | 1006249 | LN-19 & LN-20 Receipt Capacity Constraint | |||
Capacity Constraint | 05/23/25 | 05/23/25 | 1006143 | TL-400 Restrictions Remain in Effect | |||
Operational Alert | 05/05/25 | 05/05/25 | 1005876 | OFO Advisory: PL-1 FTNN Remains in Effect | |||
Maintenance | 04/23/25 | 04/23/25 | 1005719 | Lightburn Station Unit #6 Unplanned Maintenance |