Planned Service Outage 05/30/25 05/30/25 11/01/25 1735 CTPL 2025 Planned Outage and Maintenance Summary – 05.30.25
Planned Service Outage 05/27/25 05/27/25 08/31/25 1733 CTPL 2025 Planned Outage and Maintenance Summary – May 27, 2025
Planned Service Outage 04/10/25 04/10/25 07/10/25 1710 CTPL 2025 Planned Outage and Maintenance Summary – 04.10.25
Capacity Constraint 04/10/25 04/10/25 07/10/25 1709 CTPL – CT109451-GILLIS-TRUNK-R Location Off Rate - LIFTED Effective April 10, 2025
Capacity Constraint 04/09/25 04/09/25 07/09/25 1708 CTPL – CT109451-GILLIS-TRUNK-R Location Off Rate Effective April 9, 2025
Planned Service Outage 03/21/25 03/21/25 06/21/25 1689 CTPL 2025 Planned Outage and Maintenance Summary – 03.21.25