Colorado Interstate Gas Company, L.L.C. September 17, 2026 Force Majeure Cancellation – CIG Line 5A- Segment 218 (CYSC) & Segment 218 (WTNC) – Watkins to Cheyenne
|
|
Colorado Interstate Gas Company, L.L.C. (CIG) has completed repairs on Line 5A between Watkins and Cheyenne in Weld County, Colorado, and as such, CIG is lifting the Force Majeure declared in Notice No. 123243. The repair work will increase capacities effective September 17, 2026, Cycle 5 (Intraday 3) and Cycle 2 (Evening) September 18, 2026 as follows: · Segment 218 (CYSC) Cheyenne South constraint will increase from 540,000 Dth/d to 633,000 Dth/d in the TD1 direction and increase from 460,000 Dth/d to 555,000 Dth/d in the TD2 direction. · Segment 218 (WTNC) Watkins North constraint will increase from 540,000 Dth/d to 633,000 Dth/d in the TD1 direction. |
|
Pipeline Scheduling Hotline email CIGSched, or message KMRockiesSched on ICE Chat
|
Mike Burleson at (719) 640-1577 Hayden Garfield at (719) 726-5311 Matt Houtz at (719) 726-5230
|
Marketing questions
Contact your Marketing Representative. |
|
Rich Aten, Manager – Pipeline Scheduling Transportation and Storage Services Kinder Morgan Rockies Pipelines (719) 667-7527 or (719) 648-5253 richard_aten@kindermorgan.com | ICE Chat: raten
|
||
|
Colorado Interstate Gas Company, L.L.C. September 17, 2026 Force Majeure Cancellation – CIG Line 5A- Segment 218 (CYSC) & Segment 218 (WTNC) – Watkins to Cheyenne
|
|
Colorado Interstate Gas Company, L.L.C. (CIG) has completed repairs on Line 5A between Watkins and Cheyenne in Weld County, Colorado, and as such, CIG is lifting the Force Majeure declared in Notice No. 123243. The repair work will increase capacities effective September 17, 2026, Cycle 5 (Intraday 3) and Cycle 2 (Evening) September 18, 2026 as follows: · Segment 218 (CYSC) Cheyenne South constraint will increase from 540,000 Dth/d to 633,000 Dth/d in the TD1 direction and increase from 460,000 Dth/d to 555,000 Dth/d in the TD2 direction. · Segment 218 (WTNC) Watkins North constraint will increase from 540,000 Dth/d to 633,000 Dth/d in the TD1 direction. |
|
Pipeline Scheduling Hotline email CIGSched, or message KMRockiesSched on ICE Chat
|
Mike Burleson at (719) 640-1577 Hayden Garfield at (719) 726-5311 Matt Houtz at (719) 726-5230
|