Critical Notice:

Yes

Notice Type:

Force Majeure

Mode: Critical

Affected Location: System Wide

Subject:

Notice of Force Majeure Event

Cameron Interstate Pipeline (“CIP”), pursuant to Section 8.21 of the General Terms and Conditions of its

FERC Gas Tariff, hereby provides notice of Force Majeure event related to equipment failure resulting in

an unplanned compressor unit outage at its Holbrook Compressor station.

CIP experienced a compressor unit failure at the Holbrook Compressor Station. Based on preliminary

estimates, the unit will be unavailable for at least seven days. As a result of this equipment failure,

capacity through the Holbrook Station will be reduced to 1,485,000 Dth/d – effective for Gas Day April 13,

2023, and continuing until further notice.

CIP will periodically provide updates to the schedule as they become available: CIP Informational Postings

Please contact a scheduling representative if you have any questions.

Team: FrontOffice@SempraGlobal.com

Day (M-F)

Evening (M-F)

Weekend

Name:

Eric Perez

Shawnna Sallee

Katherine Silva

Office:

281.423.2704

Mobile:

832.835.7726

832.819.7292

832.492.3433

Email: EPerez@SempraGlobal.com SSallee@SempraGlobal.com KSilva@SempraGlobal.com

ICE Chat:

eperez7

ssallee

ksilva2






April 12, 2023


Critical Notice: Yes


Notice Type:
Force Majeure
Mode: Critical
Affected Location: System Wide


Subject:
Notice of Force Majeure Event


Cameron Interstate Pipeline (“CIP”), pursuant to Section 8.21 of the General Terms and Conditions of its
FERC Gas Tariff, hereby provides notice of Force Majeure event related to equipment failure resulting in
an unplanned compressor unit outage at its Holbrook Compressor station.

CIP experienced a compressor unit failure at the Holbrook Compressor Station. Based on preliminary
estimates, the unit will be unavailable for at least seven days. As a result of this equipment failure,
capacity through the Holbrook Station will be reduced to 1,485,000 Dth/d – effective for Gas Day April 13,
2023, and continuing until further notice.

CIP will periodically provide updates to the schedule as they become available: CIP Informational Postings

Please contact a scheduling representative if you have any questions.

Team: FrontOffice@SempraGlobal.com



Day (M-F)
Evening (M-F)
Weekend
Name:
Eric Perez
Shawnna Sallee
Katherine Silva
Office:
281.423.2704


Mobile:
832.835.7726
832.819.7292
832.492.3433
Email: EPerez@SempraGlobal.com SSallee@SempraGlobal.com KSilva@SempraGlobal.com
ICE Chat:
eperez7
ssallee
ksilva2