ANR Pipeline Company Notice 26249053
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TSP Name
ANR Pipeline Company
TSP
006958581
Date
Time
Notice ID
26249053
Notice Type Description: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 26249021
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/17/26
09/17/26
10/10/26
1:38:27 PM
5:00:00 AM
5:00:00 AM
Subject: UPDATED: CAPACITY REDUCTION Southeast Mainline – Defiance Westbound
Author: Diana Lopez
Notice Text
Since the last posting, ANR has revised the dates for maintenance at the Lagrange Compressor Station on the Southeast Mainline located in Lagrange, Indiana. As a result, capacity will be reduced as follows:9/28 – 10/9 (previously 9/21 – 10/2) Defiance Westbound (LOC #FPDEFNWB): 75 MMcf/d (leaving 610 MMcf/d)ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations30% - Based on the Current Contracted MDQAny reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR’s FERC Gas Tariff (“Tariff”). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR’s Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267.
ANR Pipeline Company
TSP
006958581
Date
Time
Notice ID
26249053
Notice Type Description: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 26249021
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/17/26
09/17/26
10/10/26
1:38:27 PM
5:00:00 AM
5:00:00 AM
Subject: UPDATED: CAPACITY REDUCTION Southeast Mainline – Defiance Westbound
Author: Diana Lopez
Notice Text
Since the last posting, ANR has revised the dates for maintenance at the Lagrange Compressor Station on the Southeast Mainline located in Lagrange, Indiana. As a result, capacity will be reduced as follows:9/28 – 10/9 (previously 9/21 – 10/2) Defiance Westbound (LOC #FPDEFNWB): 75 MMcf/d (leaving 610 MMcf/d)ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations30% - Based on the Current Contracted MDQAny reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR’s FERC Gas Tariff (“Tariff”). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR’s Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267.