Notice Type Description: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 25980321
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
03/18/26
03/18/26
03/19/26
5:26:47 PM
12:00:00 AM
12:00:00 AM
Subject: UPDATED CAPACITY REDUCTION - Southeast Mainline – Evangeline Southbound
Author: T0000106
Notice Text
Effective 3/18/26 ID3 cycle, ANR has completed the Eunice compressor station maintenance and is reinstating capacity at Evangeline Southbound (LOC #FPEVNGSB) to 1,087 MMcf/d (previously 987 MMcf/d). Please refer to Notice #25986109 on the EBB for additional maintenance. Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR’s FERC Gas Tariff (“Tariff”). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR’s Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
ANR Pipeline Company
TSP
006958581
Date
Time
Notice ID
25986320
Notice Type Description: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 25980321
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
03/18/26
03/18/26
03/19/26
5:26:47 PM
12:00:00 AM
12:00:00 AM
Subject: UPDATED CAPACITY REDUCTION - Southeast Mainline – Evangeline Southbound
Author: T0000106
Notice Text
Effective 3/18/26 ID3 cycle, ANR has completed the Eunice compressor station maintenance and is reinstating capacity at Evangeline Southbound (LOC #FPEVNGSB) to 1,087 MMcf/d (previously 987 MMcf/d). Please refer to Notice #25986109 on the EBB for additional maintenance. Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR’s FERC Gas Tariff (“Tariff”). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR’s Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267