ANR Pipeline Company Notice 25986124
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TSP Name
ANR Pipeline Company
TSP
006958581
Date
Time
Notice ID
25986124
Notice Type Description: Force Majeure
Notice Stat Desc: Supersede
Prior Notice: 25978017
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
03/17/26
03/17/26
06/01/26
2:18:14 PM
12:00:00 AM
12:00:00 AM
Subject: UPDATED: NOTICE OF FORCE MAJEURE ANRPL –Southeast Mainline
Author: T0000106
Notice Text
Since the last posting, ANR Pipeline Company ("ANR") has extended the FMJ through 5/31. 2/6 – 3/31 – Cottage Grove Southbound (LOC #FPSCTGGSB): 603 MMcf/d (leaving 680 MMcf/d)4/1 – 5/31 - Cottage Grove Southbound (LOC #FPSCTGGSB): 603 MMcf/d (leaving 629 MMcf/d) Estimated impact to Firm Primary as follows: 15% - Based on the Current Net Shipper Nominations 47% - Based on the Current Contracted MDQ 2/6 – 3/31 – Shelbyville Southbound (LOC #FPSHBVSB): 394 MMcf/d (leaving 670 MMcf/d) 4/1 – 5/31- Shelbyville Southbound (LOC #FPSHBVSB): 394 MMcf/d (leaving 647 MMcf/d) Estimated impact to Firm Primary as follows: 2% - Based on the Current Net Shipper Nominations 33% - Based on the Current Contracted MDQ 2/6 – 3/31 - Defiance Southbound (LOC #FPDEFNSB): 385 MMcf/d (leaving 540 MMcf/d)4/1 – 5/31 - Defiance Southbound (LOC #FPDEFNSB): 385 MMcf/d (leaving 500 MMcf/d) Estimated impact to Firm Primary as follows: 13% - Based on the Current Net Shipper Nominations 48% - Based on the Current Contracted MDQ
2/6 – 5/31 (previously 3/31) – REX Shelbyville Receipt (LOC #742252): 1,140 MMcf/d (leaving 160 MMcf/d) Estimated impact to Firm Primary as follows: 9% - Based on the Current Net Shipper Nominations 77% - Based on the Current Contracted MDQ Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Force Majeure Average Usage Quantity, as defined in Section 6.36.2(a) of ANR's Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
ANR Pipeline Company
TSP
006958581
Date
Time
Notice ID
25986124
Notice Type Description: Force Majeure
Notice Stat Desc: Supersede
Prior Notice: 25978017
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
03/17/26
03/17/26
06/01/26
2:18:14 PM
12:00:00 AM
12:00:00 AM
Subject: UPDATED: NOTICE OF FORCE MAJEURE ANRPL –Southeast Mainline
Author: T0000106
Notice Text
Since the last posting, ANR Pipeline Company ("ANR") has extended the FMJ through 5/31. 2/6 – 3/31 – Cottage Grove Southbound (LOC #FPSCTGGSB): 603 MMcf/d (leaving 680 MMcf/d)4/1 – 5/31 - Cottage Grove Southbound (LOC #FPSCTGGSB): 603 MMcf/d (leaving 629 MMcf/d) Estimated impact to Firm Primary as follows: 15% - Based on the Current Net Shipper Nominations 47% - Based on the Current Contracted MDQ 2/6 – 3/31 – Shelbyville Southbound (LOC #FPSHBVSB): 394 MMcf/d (leaving 670 MMcf/d) 4/1 – 5/31- Shelbyville Southbound (LOC #FPSHBVSB): 394 MMcf/d (leaving 647 MMcf/d) Estimated impact to Firm Primary as follows: 2% - Based on the Current Net Shipper Nominations 33% - Based on the Current Contracted MDQ 2/6 – 3/31 - Defiance Southbound (LOC #FPDEFNSB): 385 MMcf/d (leaving 540 MMcf/d)4/1 – 5/31 - Defiance Southbound (LOC #FPDEFNSB): 385 MMcf/d (leaving 500 MMcf/d) Estimated impact to Firm Primary as follows: 13% - Based on the Current Net Shipper Nominations 48% - Based on the Current Contracted MDQ
2/6 – 5/31 (previously 3/31) – REX Shelbyville Receipt (LOC #742252): 1,140 MMcf/d (leaving 160 MMcf/d) Estimated impact to Firm Primary as follows: 9% - Based on the Current Net Shipper Nominations 77% - Based on the Current Contracted MDQ Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Force Majeure Average Usage Quantity, as defined in Section 6.36.2(a) of ANR's Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267