Post
Notice Effective
Notice End

Response

03/16/26
03/16/26
11/01/26



3:49:21 PM
12:00:00 AM
12:00:00 AM



Subject: UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound

Author: T0000106

Notice Text

ANR has extended the maintenance at the Havensville Compressor Station on the Southwest Mainline through 10/31/26 (previously 3/31/26). As a result, capacity will be reduced as follows:  2/9 – 3/31  SWML Northbound (LOC #FPSWMLNB): 131 MMcf/d (leaving 600 MMcf/d)4/1 – 10/31 SWML Northbound (LOC #FPSWMLNB): 116 MMcf/d (leaving 590 MMcf/d)

ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments.Estimated impact to Firm Primary as follows:                 18% - Based on the Current Net Shipper Nominations                  12% - Based on the Current Contracted MDQAny reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR’s FERC Gas Tariff (“Tariff”).  However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage.  In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR’s Tariff, less any scheduled quantities on the contract.Please refer to critical notices for any additional capacity impacts.Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267