ANR Pipeline Company Notice 25978823

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name

ANR Pipeline Company

TSP

006958581

Date

Time

Notice ID

25978823

Notice Type Description: Maintenance
Notice Stat Desc: Supersede
Prior Notice: 25977817
Critical: Y
Reqrd Rsp Desc: No Response Required

Post
Notice Effective
Notice End

Response

02/12/26
02/12/26
04/01/26



11:00:35 AM
12:00:00 AM
12:00:00 AM



Subject: UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound

Author: T0000106

Notice Text

ANR has extended the maintenance at the Havensville Compressor Station on the Southwest Mainline. As a result, capacity will be reduced as follows:  2/9 – 3/31 (previously 2/28) SWML Northbound (LOC #FPSWMLNB): 131 MMcf/d (leaving 600 MMcf/d)

ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments.Estimated impact to Firm Primary as follows:                 18% - Based on the Current Net Shipper Nominations                  12% - Based on the Current Contracted MDQAny reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR’s FERC Gas Tariff (“Tariff”).  However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage.  In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR’s Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267