Posting Date: August 21, 2026
Planned Service Outage – Maintenance Project #26.021
Impact Area –Quakertown Compressor Station
Outage Dates: October 15,2026
As a supplement to the previously posted maintenance summary for Project # 26.021, under
Planned Service Outages on the informational postings site, Adelphia Gateway, LLC
(“Adelphia”), is providing additional clarification of restrictions.
As a result of this work, the operational available capacity at the following location(s)
will be set to zero at 9:00 AM CPT with the start of gas day October 15, 2026 with an
anticipated return to service at 9:00 AM CPT for gas day October 16, 2026.
ZONE
LOCATION NAME
DIRECTION OF FLOW
OPERATIONAL
AVAILABLE CAPACITY
North A
Tetco Quakertown
Receipt
0
Please note customers may continue to use all other North A Zone receipt points, including
Transco Lower Mud Run Road A and Columbia Gilbert.
As the project progresses, Adelphia will post updates as available.
The current schedule for this planned service outage and its anticipated impacts is subject
to change, so please monitor critical notices, including the Adelphia’s Planned Outage and
Maintenance Summary on Info Posts for any updates to this project or others.
Contact your Transportation or Marketing Services Representative with any questions.
Posting Date: August 21, 2026
Planned Service Outage – Maintenance Project #26.021
Impact Area –Quakertown Compressor Station
Outage Dates: October 15,2026
As a supplement to the previously posted maintenance summary for Project # 26.021, under
Planned Service Outages on the informational postings site, Adelphia Gateway, LLC
(“Adelphia”), is providing additional clarification of restrictions.
As a result of this work, the operational available capacity at the following location(s)
will be set to zero at 9:00 AM CPT with the start of gas day October 15, 2026 with an
anticipated return to service at 9:00 AM CPT for gas day October 16, 2026.
ZONE
LOCATION NAME
DIRECTION OF FLOW
OPERATIONAL
AVAILABLE CAPACITY
North A
Tetco Quakertown
Receipt
0
Please note customers may continue to use all other North A Zone receipt points, including
Transco Lower Mud Run Road A and Columbia Gilbert.
As the project progresses, Adelphia will post updates as available.
The current schedule for this planned service outage and its anticipated impacts is subject
to change, so please monitor critical notices, including the Adelphia’s Planned Outage and
Maintenance Summary on Info Posts for any updates to this project or others.
Contact your Transportation or Marketing Services Representative with any questions.