Westcoast Energy Icon

Huntingdon/Station 2 South Capacity for September 19-21, 2026

Westcoast Energy 3w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Critical Notice Description: Critical Notices

Notice Effective Date / Time: 09/18/2026 06:35:00 AM

Notice End Date / Time: 12/17/2026 06:35:00 AM

Notice Identifier: 183141

Notice Status Description: Initiate

Notice Type: Capacity Constraint

Posting Date / Time: 09/17/2026 05:09:35 PM

Prior Notice Identifier: None

Required Response Indicator Description: No response required

Response Date / Time: None

Subject: Huntingdon/Station 2 South Capacity for September 19-21, 2026

Notice Text:

Further to notice #182135, Westcoast will be allowing the following flow on T South:

Huntingdon Delivery Area Capacity

September 19 - 21, 2026: 1,858,760 GJ

Station 2 South Capacity

September 19 - 21, 2026: 1,076,458 GJ

The constraint is below Firm Contracted Capacity. Shippers can access the Constrained Locations Firm Shipper Share Report for more detailed information (Nominations>Scheduled Quantity>Constrained Locations Firm Shipper Share).

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.



Critical Notice Description: Critical Notices

Notice Effective Date / Time: 09/18/2026 06:35:00 AM

Notice End Date / Time: 12/17/2026 06:35:00 AM

Notice Identifier: 183141

Notice Status Description: Initiate

Notice Type: Capacity Constraint

Posting Date / Time: 09/17/2026 05:09:35 PM

Prior Notice Identifier: None

Required Response Indicator Description: No response required

Response Date / Time: None

Subject: Huntingdon/Station 2 South Capacity for September 19-21, 2026

Notice Text:

Further to notice #182135, Westcoast will be allowing the following flow on T South:

Huntingdon Delivery Area Capacity

September 19 - 21, 2026: 1,858,760 GJ

Station 2 South Capacity

September 19 - 21, 2026: 1,076,458 GJ

The constraint is below Firm Contracted Capacity. Shippers can access the Constrained Locations Firm Shipper Share Report for more detailed information (Nominations>Scheduled Quantity>Constrained Locations Firm Shipper Share).

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.