26" Alberta West/FSJML to Station 2 September Outage Update
Westcoast Energy 2mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP: 
TSP Name: 
Critical Notice Description: 
Notice Effective Date: 
Notice Effective Time: 
Notice End Date: 
Notice End Time: 
Notice Identifier: 
Notice Status Description: 
Notice Type: 
Posting Date: 
Posting Time: 
Prior Notice Identifier: 
Required Response
Indicator Description: 
Response Date: 
Response Time: 
Subject: 
TSP Name: 
Critical Notice Description: 
Notice Effective Date: 
Notice Effective Time: 
Notice End Date: 
Notice End Time: 
Notice Identifier: 
Notice Status Description: 
Notice Type: 
Posting Date: 
Posting Time: 
Prior Notice Identifier: 
Required Response
Indicator Description: 
Response Date: 
Response Time: 
Subject: 
243346247
Westcoast Energy Limited Partnership
Critical notice
08/04/2026
01:55:30 PM
11/02/2026
12:19:30 PM
181244
Initiate
Capacity Constraint
08/04/2026
01:55:30 PM
No response required
26" Alberta West/FSJML to Station 2 September Outage Update
Westcoast Energy Limited Partnership
Critical notice
08/04/2026
01:55:30 PM
11/02/2026
12:19:30 PM
181244
Initiate
Capacity Constraint
08/04/2026
01:55:30 PM
No response required
26" Alberta West/FSJML to Station 2 September Outage Update
Notice Text:
Westcoast has determined that the South Taylor Hill Tie-ins, previously scheduled for September 8 - 19, have been rescheduled for September 13 - 25 and will not require the previously anticipated 26" Alberta West Capacity reduction.
As a result, 26" Alberta West Capacity will return to its annual capacity of 368,433 GJ. MS 84 and MS 204 will be required to remain isolated for the duration of the work.
If you have any questions, please contact the CSR hotline at (403) 699-1800.
TSP: 
TSP Name: 
Critical Notice Description: 
Notice Effective Date: 
Notice Effective Time: 
Notice End Date: 
Notice End Time: 
Notice Identifier: 
Notice Status Description: 
Notice Type: 
Posting Date: 
Posting Time: 
Prior Notice Identifier: 
Required Response
Indicator Description: 
Response Date: 
Response Time: 
Subject: 
TSP Name: 
Critical Notice Description: 
Notice Effective Date: 
Notice Effective Time: 
Notice End Date: 
Notice End Time: 
Notice Identifier: 
Notice Status Description: 
Notice Type: 
Posting Date: 
Posting Time: 
Prior Notice Identifier: 
Required Response
Indicator Description: 
Response Date: 
Response Time: 
Subject: 
243346247
Westcoast Energy Limited Partnership
Critical notice
08/04/2026
01:55:30 PM
11/02/2026
12:19:30 PM
181244
Initiate
Capacity Constraint
08/04/2026
01:55:30 PM
No response required
26" Alberta West/FSJML to Station 2 September Outage Update
Westcoast Energy Limited Partnership
Critical notice
08/04/2026
01:55:30 PM
11/02/2026
12:19:30 PM
181244
Initiate
Capacity Constraint
08/04/2026
01:55:30 PM
No response required
26" Alberta West/FSJML to Station 2 September Outage Update
Notice Text:
Westcoast has determined that the South Taylor Hill Tie-ins, previously scheduled for September 8 - 19, have been rescheduled for September 13 - 25 and will not require the previously anticipated 26" Alberta West Capacity reduction.
As a result, 26" Alberta West Capacity will return to its annual capacity of 368,433 GJ. MS 84 and MS 204 will be required to remain isolated for the duration of the work.
If you have any questions, please contact the CSR hotline at (403) 699-1800.