COMPLETE: Planned Service Outage - Flow South of Angus CS #2204 - Capacity Constraint
Viking Gas Transmission Company 2w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP: 609166673
TSP Name: Viking Gas Transmission Company
Posting Date/Time: 06/25/2026 16:20:34
Notice Identifier: 172
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: COMPLETE: Planned Service Outage - Flow South of Angus CS #2204 - Capacity Constraint
Notice Eff Date/Time: 06/25/2026 00:00:00
Notice End Date/Time: 06/26/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1533
Notice Text:
The planned maintenance at the Angus Compressor Station (CS) #2204 is now complete.
Effective Gas Day, Friday, June 26, 2026, Timely Cycle, the flow South of Angus CS #2204 receipt capacity will be increased from 500,000 Dth to 564,904 Dth.
Please contact your Commercial representative with any further questions.
----------------------------------------------------
Prior Notice ID: 167
The planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) has been postponed. The flow South of Angus CS #2204 receipt capacity is now beginning on Gas Day, Tuesday, June 23, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 25, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
----------------------------------------------------
Prior Notice ID: 156
Due to planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease the flow South of Angus CS #2204 receipt capacity beginning Gas Day, Tuesday, June 16, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 18, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
TSP Name: Viking Gas Transmission Company
Posting Date/Time: 06/25/2026 16:20:34
Notice Identifier: 172
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: COMPLETE: Planned Service Outage - Flow South of Angus CS #2204 - Capacity Constraint
Notice Eff Date/Time: 06/25/2026 00:00:00
Notice End Date/Time: 06/26/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1533
Notice Text:
The planned maintenance at the Angus Compressor Station (CS) #2204 is now complete.
Effective Gas Day, Friday, June 26, 2026, Timely Cycle, the flow South of Angus CS #2204 receipt capacity will be increased from 500,000 Dth to 564,904 Dth.
Please contact your Commercial representative with any further questions.
----------------------------------------------------
Prior Notice ID: 167
The planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) has been postponed. The flow South of Angus CS #2204 receipt capacity is now beginning on Gas Day, Tuesday, June 23, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 25, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
----------------------------------------------------
Prior Notice ID: 156
Due to planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease the flow South of Angus CS #2204 receipt capacity beginning Gas Day, Tuesday, June 16, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 18, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
TSP: 609166673
TSP Name: Viking Gas Transmission Company
Posting Date/Time: 06/25/2026 16:20:34
Notice Identifier: 172
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: COMPLETE: Planned Service Outage - Flow South of Angus CS #2204 - Capacity Constraint
Notice Eff Date/Time: 06/25/2026 00:00:00
Notice End Date/Time: 06/26/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1533
Notice Text:
The planned maintenance at the Angus Compressor Station (CS) #2204 is now complete.
Effective Gas Day, Friday, June 26, 2026, Timely Cycle, the flow South of Angus CS #2204 receipt capacity will be increased from 500,000 Dth to 564,904 Dth.
Please contact your Commercial representative with any further questions.
----------------------------------------------------
Prior Notice ID: 167
The planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) has been postponed. The flow South of Angus CS #2204 receipt capacity is now beginning on Gas Day, Tuesday, June 23, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 25, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
----------------------------------------------------
Prior Notice ID: 156
Due to planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease the flow South of Angus CS #2204 receipt capacity beginning Gas Day, Tuesday, June 16, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 18, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
TSP Name: Viking Gas Transmission Company
Posting Date/Time: 06/25/2026 16:20:34
Notice Identifier: 172
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: COMPLETE: Planned Service Outage - Flow South of Angus CS #2204 - Capacity Constraint
Notice Eff Date/Time: 06/25/2026 00:00:00
Notice End Date/Time: 06/26/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1533
Notice Text:
The planned maintenance at the Angus Compressor Station (CS) #2204 is now complete.
Effective Gas Day, Friday, June 26, 2026, Timely Cycle, the flow South of Angus CS #2204 receipt capacity will be increased from 500,000 Dth to 564,904 Dth.
Please contact your Commercial representative with any further questions.
----------------------------------------------------
Prior Notice ID: 167
The planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) has been postponed. The flow South of Angus CS #2204 receipt capacity is now beginning on Gas Day, Tuesday, June 23, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 25, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
----------------------------------------------------
Prior Notice ID: 156
Due to planned maintenance at the Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease the flow South of Angus CS #2204 receipt capacity beginning Gas Day, Tuesday, June 16, 2026, Timely Cycle.
This capacity constraint is anticipated to be in effect through Gas Day Thursday, June 18, 2026.
Flow South of Angus CS #2204 receipt capacity will be reduced from 564,904 Dth to 500,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.