Notice of Force Majeure Event - Unplanned Outage Station 50 Main Unit 9
Transco 1w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| Critical: | Y |
| Notice Eff Date: | 09/28/2026 |
| Notice Eff Time: | 13:27:51 CDT |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 17324005 |
| Notice Stat Desc: | Initiate |
| Notice Type Desc: | Force Maj |
| Post Date: | 09/28/2026 |
| Post Time: | 13:27:51 CDT |
| Prior Notice: | |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Notice of Force Majeure Event - Unplanned Outage Station 50 Main Unit 9
Transcontinental Gas Pipe Line Company, LLC ("Transco"), pursuant to Section 11 of the General Terms and Conditions of its FERC Gas Tariff, hereby provides notice of a Force Majeure event resulting in an unplanned outage at Compressor Station 50 due to equipment failure on Main Unit 9.
Transco must immediately restrict scheduled quantities moving south to north through the TSB below. The constraint will be effective timely gas day 9/29/2026. An updated posting with an estimated return to service date will be provided no later than Wednesday, September 30, 2026. All efforts are being made to return Main Unit 9 to service as quickly as possible.
The receipt-based Throughput Section Boundary (TSB) at mainline MP 517 (Station 50) will be used to manage capacity availability during this outage. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.
Location ID | Flow Direction | |
COMPRESSOR STATION W 50 MP 517.23 | 9013363 | South to North |
Estimated Outage | Design Capacity (Mdt/d) | Total Qty Available (Mdt/d) | % Available Total Primary-Firm vs Design Capacity | % Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization) |
9/29 Timely - UFN | 1,536 | 1,300 | 85% | 5-12% |
If you have any questions, please contact your Transportation Services Representative.
| Critical: | Y |
| Notice Eff Date: | 09/28/2026 |
| Notice Eff Time: | 13:27:51 CDT |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 17324005 |
| Notice Stat Desc: | Initiate |
| Notice Type Desc: | Force Maj |
| Post Date: | 09/28/2026 |
| Post Time: | 13:27:51 CDT |
| Prior Notice: | |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Notice of Force Majeure Event - Unplanned Outage Station 50 Main Unit 9
Transcontinental Gas Pipe Line Company, LLC ("Transco"), pursuant to Section 11 of the General Terms and Conditions of its FERC Gas Tariff, hereby provides notice of a Force Majeure event resulting in an unplanned outage at Compressor Station 50 due to equipment failure on Main Unit 9.
Transco must immediately restrict scheduled quantities moving south to north through the TSB below. The constraint will be effective timely gas day 9/29/2026. An updated posting with an estimated return to service date will be provided no later than Wednesday, September 30, 2026. All efforts are being made to return Main Unit 9 to service as quickly as possible.
The receipt-based Throughput Section Boundary (TSB) at mainline MP 517 (Station 50) will be used to manage capacity availability during this outage. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.
Location ID | Flow Direction | |
COMPRESSOR STATION W 50 MP 517.23 | 9013363 | South to North |
Estimated Outage | Design Capacity (Mdt/d) | Total Qty Available (Mdt/d) | % Available Total Primary-Firm vs Design Capacity | % Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization) |
9/29 Timely - UFN | 1,536 | 1,300 | 85% | 5-12% |
If you have any questions, please contact your Transportation Services Representative.