Job 888958 Washington Storage Planned Outage and Maintenance Summary

Transco 1mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 08/20/2026
Notice Eff Time: 10:43:39 CDT
Notice End Date:
Notice End Time:
Notice ID: 17185268
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 08/20/2026
Post Time: 10:43:39 CDT
Prior Notice:
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job 888958 Washington Storage Planned Outage and Maintenance Summary

Transco’s Job # 888958, as referenced in Transco’s Planned Outage and Maintenance Summary is currently scheduled to begin on October 13, 2026 through October 19, 2026.

During this period, Station 54 and the associated Washington storage facility will not be available as it must be shut-in to complete required DOT compliance testing. Services under all WSS rate schedules may not be available during this period due to Operating Conditions resulting from this planned equipment outage. 

Transco will allow injections and withdrawals on a net basis during this period. Scheduled injections will be limited up to the scheduled withdrawal quantity. If Transco is required to further restrict WSS injections, additional advance notice may be limited. The scheduling of WSS withdrawal services is not expected to be impacted

This work will also reduce system flexibility and recommend all parties maintain a concurrent balance of receipts and deliveries daily.

If you have any questions, please contact your Transportation Service representative.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 08/20/2026
Notice Eff Time: 10:43:39 CDT
Notice End Date:
Notice End Time:
Notice ID: 17185268
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 08/20/2026
Post Time: 10:43:39 CDT
Prior Notice:
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job 888958 Washington Storage Planned Outage and Maintenance Summary

Transco’s Job # 888958, as referenced in Transco’s Planned Outage and Maintenance Summary is currently scheduled to begin on October 13, 2026 through October 19, 2026.

During this period, Station 54 and the associated Washington storage facility will not be available as it must be shut-in to complete required DOT compliance testing. Services under all WSS rate schedules may not be available during this period due to Operating Conditions resulting from this planned equipment outage. 

Transco will allow injections and withdrawals on a net basis during this period. Scheduled injections will be limited up to the scheduled withdrawal quantity. If Transco is required to further restrict WSS injections, additional advance notice may be limited. The scheduling of WSS withdrawal services is not expected to be impacted

This work will also reduce system flexibility and recommend all parties maintain a concurrent balance of receipts and deliveries daily.

If you have any questions, please contact your Transportation Service representative.