Transco Icon

Unplanned Maintenance Station 50 Compressor Outage

Transco 2w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 06/23/2026
Notice Eff Time: 10:41:27 CDT
Notice End Date:
Notice End Time:
Notice ID: 16987620
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 06/23/2026
Post Time: 10:41:27 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Unplanned Maintenance Station 50 Compressor Outage

Due to an equipment failure on Main Unit 9 at Station 50, Transco must immediately restrict scheduled quantities moving south to north through the TSB below. The constraint will be effective ID1, 6/23/2026. The duration of this outage is anticipated to be 1 day.

The receipt-based Throughput Section Boundary (TSB) at mainline MP 517 (Station 50) will be used to manage capacity availability during this outage. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.

TSB Name Location

Location ID

Flow Direction

COMPRESSOR STATION W 50 MP 517.23 

9013363

South to North

 

 

Estimated Outage

Design Capacity (Mdt/d)

Total Qty Available (Mdt/d)

% Available Total Primary-Firm vs Design Capacity

% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization)   

June 23, 2026

1,536

1,420

92%

5-10%

 

 

If you have any questions, please contact your Transportation Services Representative.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 06/23/2026
Notice Eff Time: 10:41:27 CDT
Notice End Date:
Notice End Time:
Notice ID: 16987620
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 06/23/2026
Post Time: 10:41:27 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Unplanned Maintenance Station 50 Compressor Outage

Due to an equipment failure on Main Unit 9 at Station 50, Transco must immediately restrict scheduled quantities moving south to north through the TSB below. The constraint will be effective ID1, 6/23/2026. The duration of this outage is anticipated to be 1 day.

The receipt-based Throughput Section Boundary (TSB) at mainline MP 517 (Station 50) will be used to manage capacity availability during this outage. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.

TSB Name Location

Location ID

Flow Direction

COMPRESSOR STATION W 50 MP 517.23 

9013363

South to North

 

 

Estimated Outage

Design Capacity (Mdt/d)

Total Qty Available (Mdt/d)

% Available Total Primary-Firm vs Design Capacity

% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization)   

June 23, 2026

1,536

1,420

92%

5-10%

 

 

If you have any questions, please contact your Transportation Services Representative.