Station 40 ESD (Job 249679) 2026 Planned Outage and Maintenance Summary
Transco 5d ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| Critical: | Y |
| Notice Eff Date: | 05/21/2026 |
| Notice Eff Time: | 10:39:00 CDT |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 16880918 |
| Notice Stat Desc: | Initiate |
| Notice Type Desc: | Maint |
| Post Date: | 05/21/2026 |
| Post Time: | 10:39:00 CDT |
| Prior Notice: | 0 |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Station 40 ESD (Job 249679) 2026 Planned Outage and Maintenance Summary
Transco will be performing a necessary compressor station outage associated with Job #249679 on its 2026 Planned Outage and Maintenance Summary. This outage is required to perform testing of safety systems at the facility. The current schedule for this maintenance is July 21, 2026 through July 23, 2026.
Operating conditions resulting from this work will require Transco to limit scheduled quantities for all transportation priorities moving south to north through the location indicated below.
The location Throughput Section Boundaries (“TSB”) for Station 40 at mainline milepost 389.19 S-N will be used to manage capacity availability during this planned work. An updated Market and Production Area constraint notice will include the TSB and the available quantity of all transportation services during the indicated period.
|
TSB Name - Location |
Location ID |
Flow Direction |
|
Sta 40 MP 389.19 S to N |
9011480 |
South to North |
|
Estimated Outage |
Design Capacity (Mdt/d) |
Total Qty Available (Mdt/d) |
% Available Total Primary-Firm vs Design Capacity |
% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization) |
|
July 21-23 |
709 |
534 |
75% |
15-20% |
If you have any questions, please contact your Transportation Services Representative.
| Critical: | Y |
| Notice Eff Date: | 05/21/2026 |
| Notice Eff Time: | 10:39:00 CDT |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 16880918 |
| Notice Stat Desc: | Initiate |
| Notice Type Desc: | Maint |
| Post Date: | 05/21/2026 |
| Post Time: | 10:39:00 CDT |
| Prior Notice: | 0 |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Station 40 ESD (Job 249679) 2026 Planned Outage and Maintenance Summary
Transco will be performing a necessary compressor station outage associated with Job #249679 on its 2026 Planned Outage and Maintenance Summary. This outage is required to perform testing of safety systems at the facility. The current schedule for this maintenance is July 21, 2026 through July 23, 2026.
Operating conditions resulting from this work will require Transco to limit scheduled quantities for all transportation priorities moving south to north through the location indicated below.
The location Throughput Section Boundaries (“TSB”) for Station 40 at mainline milepost 389.19 S-N will be used to manage capacity availability during this planned work. An updated Market and Production Area constraint notice will include the TSB and the available quantity of all transportation services during the indicated period.
|
TSB Name - Location |
Location ID |
Flow Direction |
|
Sta 40 MP 389.19 S to N |
9011480 |
South to North |
|
Estimated Outage |
Design Capacity (Mdt/d) |
Total Qty Available (Mdt/d) |
% Available Total Primary-Firm vs Design Capacity |
% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization) |
|
July 21-23 |
709 |
534 |
75% |
15-20% |
If you have any questions, please contact your Transportation Services Representative.