Job 327549 & 477378 Mainline B & Station 155 2026 Planned Outage and Maintenance Summary

Transco 3w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 04/30/2026
Notice Eff Time: 11:03:09 CDT
Notice End Date:
Notice End Time:
Notice ID: 16817803
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 04/30/2026
Post Time: 11:03:09 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job 327549 & 477378 Mainline B & Station 155 2026 Planned Outage and Maintenance Summary

Transco will be performing a pipeline and compressor station outage associated with Jobs 327549 & 477378 on its 2026 Planned Outage and Maintenance Summary. Work will occur on Mainline B between Stations 155 and 160 and at Station 155, both outages are associated with the Southeast Supply Enhancement expansion project. This activity will impact the availability of Primary Firm transportation services moving North to South on the Transco Mainline through Station 160.

The current schedule for this maintenance is Tuesday July 7, 2026 through Saturday August 29, 2026.

The below Throughput Section Boundary (TSB) will be used to manage capacity availability during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.

TSB Name- Location

Location ID

Flow Direction

Compressor Station 160

9012663

N-S

 

 

Estimated Outage

Design Capacity (Mdt/d)

Total Primary Firm Qty Available (Mdt/d)

%Cuts (Primary)-Potential Shipper Impact (Based on Historical Utilization)

07/07-08/29

2,221

1,726

15-25%

 

 

If you have any questions, please contact your Transportation Services Representative.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 04/30/2026
Notice Eff Time: 11:03:09 CDT
Notice End Date:
Notice End Time:
Notice ID: 16817803
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 04/30/2026
Post Time: 11:03:09 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job 327549 & 477378 Mainline B & Station 155 2026 Planned Outage and Maintenance Summary

Transco will be performing a pipeline and compressor station outage associated with Jobs 327549 & 477378 on its 2026 Planned Outage and Maintenance Summary. Work will occur on Mainline B between Stations 155 and 160 and at Station 155, both outages are associated with the Southeast Supply Enhancement expansion project. This activity will impact the availability of Primary Firm transportation services moving North to South on the Transco Mainline through Station 160.

The current schedule for this maintenance is Tuesday July 7, 2026 through Saturday August 29, 2026.

The below Throughput Section Boundary (TSB) will be used to manage capacity availability during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.

TSB Name- Location

Location ID

Flow Direction

Compressor Station 160

9012663

N-S

 

 

Estimated Outage

Design Capacity (Mdt/d)

Total Primary Firm Qty Available (Mdt/d)

%Cuts (Primary)-Potential Shipper Impact (Based on Historical Utilization)

07/07-08/29

2,221

1,726

15-25%

 

 

If you have any questions, please contact your Transportation Services Representative.