Job 327549 & 477378 Mainline B & Station 155 2026 Planned Outage and Maintenance Summary
Transco 3w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| Critical: | Y |
| Notice Eff Date: | 04/30/2026 |
| Notice Eff Time: | 11:03:09 CDT |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 16817803 |
| Notice Stat Desc: | Initiate |
| Notice Type Desc: | Maint |
| Post Date: | 04/30/2026 |
| Post Time: | 11:03:09 CDT |
| Prior Notice: | 0 |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Job 327549 & 477378 Mainline B & Station 155 2026 Planned Outage and Maintenance Summary
Transco will be performing a pipeline and compressor station outage associated with Jobs 327549 & 477378 on its 2026 Planned Outage and Maintenance Summary. Work will occur on Mainline B between Stations 155 and 160 and at Station 155, both outages are associated with the Southeast Supply Enhancement expansion project. This activity will impact the availability of Primary Firm transportation services moving North to South on the Transco Mainline through Station 160.
The current schedule for this maintenance is Tuesday July 7, 2026 through Saturday August 29, 2026.
The below Throughput Section Boundary (TSB) will be used to manage capacity availability during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.
|
TSB Name- Location |
Location ID |
Flow Direction |
|
Compressor Station 160 |
9012663 |
N-S |
|
Estimated Outage |
Design Capacity (Mdt/d) |
Total Primary Firm Qty Available (Mdt/d) |
%Cuts (Primary)-Potential Shipper Impact (Based on Historical Utilization) |
|
07/07-08/29 |
2,221 |
1,726 |
15-25% |
If you have any questions, please contact your Transportation Services Representative.
| Critical: | Y |
| Notice Eff Date: | 04/30/2026 |
| Notice Eff Time: | 11:03:09 CDT |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 16817803 |
| Notice Stat Desc: | Initiate |
| Notice Type Desc: | Maint |
| Post Date: | 04/30/2026 |
| Post Time: | 11:03:09 CDT |
| Prior Notice: | 0 |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Job 327549 & 477378 Mainline B & Station 155 2026 Planned Outage and Maintenance Summary
Transco will be performing a pipeline and compressor station outage associated with Jobs 327549 & 477378 on its 2026 Planned Outage and Maintenance Summary. Work will occur on Mainline B between Stations 155 and 160 and at Station 155, both outages are associated with the Southeast Supply Enhancement expansion project. This activity will impact the availability of Primary Firm transportation services moving North to South on the Transco Mainline through Station 160.
The current schedule for this maintenance is Tuesday July 7, 2026 through Saturday August 29, 2026.
The below Throughput Section Boundary (TSB) will be used to manage capacity availability during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of all transportation services during the indicated period.
|
TSB Name- Location |
Location ID |
Flow Direction |
|
Compressor Station 160 |
9012663 |
N-S |
|
Estimated Outage |
Design Capacity (Mdt/d) |
Total Primary Firm Qty Available (Mdt/d) |
%Cuts (Primary)-Potential Shipper Impact (Based on Historical Utilization) |
|
07/07-08/29 |
2,221 |
1,726 |
15-25% |
If you have any questions, please contact your Transportation Services Representative.