Notice of Force Majeure Event - Unplanned Equipment Outage Station 115
Transco 1w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| Critical: | Y |
| Notice Eff Date: | 02/11/2026 |
| Notice Eff Time: | 13:47:47 CST |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 16555673 |
| Notice Stat Desc: | Supersede |
| Notice Type Desc: | Force Maj |
| Post Date: | 02/11/2026 |
| Post Time: | 13:47:47 CST |
| Prior Notice: | 16544208 |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Notice of Force Majeure Event - Unplanned Equipment Outage Station 115
Subject: Update - Notice of Force Majeure Event - Unplanned Equipment Outage Station 115
Update: Due to improved system conditions, the available capacity will be increased per the table below, effective February 12, 2026. Work to resolve the issue is ongoing with the return to service timeline and is still TBD. Additional updates and a more accurate timeline will be provided as more information becomes available.
Transcontinental Gas Pipe Line Company, LLC (“Transco”), pursuant to Section 11 of the General Terms and Conditions of its FERC Gas Tariff, hereby provides an update to the force majeure event involving the unplanned outage at Compressor Station 115.
Operating Conditions resulting from this work will require Transco to restrict scheduled quantities for all transportation priorities moving South to North through the location indicated below. Transactions moving North to South through this location will not be impacted.
The delivery-based Throughput Section Boundary (TSB) at mainline milepost 1007.66 will be used to manage capacity during this unplanned work.
|
TSB Name - Location |
Location ID |
Flow Direction |
|
Station 115 MP 1007.66 |
9011120 |
South to North |
|
Estimated Outage |
Design Capacity (Mdth/d) |
Total Primary Firm Qty Available (Mdth/d) |
%Cuts (Primary)-Potential Shipper Impact (Based on Historical Utilization) |
|
February 8, 2026 (ID2), – February 11, 2026 |
4,746 |
|
|
|
February 12, 2026 -TBD |
4,746 |
3,950 |
0 – 5% |
If you have any questions, please contact your Transportation Services Representative.
| Critical: | Y |
| Notice Eff Date: | 02/11/2026 |
| Notice Eff Time: | 13:47:47 CST |
| Notice End Date: | |
| Notice End Time: | |
| Notice ID: | 16555673 |
| Notice Stat Desc: | Supersede |
| Notice Type Desc: | Force Maj |
| Post Date: | 02/11/2026 |
| Post Time: | 13:47:47 CST |
| Prior Notice: | 16544208 |
| Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
| Rsp Date: | |
| Rsp Time: | |
| TSP: | 007933021 |
| TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Notice of Force Majeure Event - Unplanned Equipment Outage Station 115
Subject: Update - Notice of Force Majeure Event - Unplanned Equipment Outage Station 115
Update: Due to improved system conditions, the available capacity will be increased per the table below, effective February 12, 2026. Work to resolve the issue is ongoing with the return to service timeline and is still TBD. Additional updates and a more accurate timeline will be provided as more information becomes available.
Transcontinental Gas Pipe Line Company, LLC (“Transco”), pursuant to Section 11 of the General Terms and Conditions of its FERC Gas Tariff, hereby provides an update to the force majeure event involving the unplanned outage at Compressor Station 115.
Operating Conditions resulting from this work will require Transco to restrict scheduled quantities for all transportation priorities moving South to North through the location indicated below. Transactions moving North to South through this location will not be impacted.
The delivery-based Throughput Section Boundary (TSB) at mainline milepost 1007.66 will be used to manage capacity during this unplanned work.
|
TSB Name - Location |
Location ID |
Flow Direction |
|
Station 115 MP 1007.66 |
9011120 |
South to North |
|
Estimated Outage |
Design Capacity (Mdth/d) |
Total Primary Firm Qty Available (Mdth/d) |
%Cuts (Primary)-Potential Shipper Impact (Based on Historical Utilization) |
|
February 8, 2026 (ID2), – February 11, 2026 |
4,746 |
|
|
|
February 12, 2026 -TBD |
4,746 |
3,950 |
0 – 5% |
If you have any questions, please contact your Transportation Services Representative.