Transco Icon

Job #1077537 Station 115 MLA DOT Planned Outage and Maintenance Summary

Transco 1d ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 04/29/2025
Notice Eff Time: 09:46:28 CDT
Notice End Date:
Notice End Time:
Notice ID: 15619259
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 04/29/2025
Post Time: 09:46:28 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job #1077537 Station 115 MLA DOT Planned Outage and Maintenance Summary

Transco will be performing necessary maintenance associated with Job #1077537 on its 2025 Planned Outage and Maintenance Summary.  A pipeline outage is needed to perform a DOT replacement as required by regulation due to recent DOT Class Location changes near Station 115 on Mainline A adjacent to the station. This maintenance outage will impact the availability of transportation services moving south to north through Compressor Station 115.  The current schedule is to complete the work from June 16, 2025 through August 4, 2025.

During this period of planned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving south to north through the location may not be available.

Transco will be required to manage transportation services moving south to north through the TSB location listed below. The total quantity available will be contingent on system conditions during the maintenance period and is anticipated to be initially limited to the quantities indicated below. Transactions moving north to south through this location will not be impacted.

The receipt-based Throughput Section Boundary (TSB) at Mainline MP 1031 will be used to manage capacity availability, including any required changes to the expected total quantities available during this planned work indicated below. An updated Market and Production Area constraint notice will include the location and the available quantity of primary-firm transportation services during the indicated periods. 

 

TSB Name – Location  

Location ID  

Flow Direction  

Design Capacity (Mdt/d)  

Total Primary-Firm Quantity Available (Mdt/d) 

% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization)   

Mainline MP 1031

9013083 

South to North  

4,524

See Below

0-10%

 

Pipeline Maintenance

Estimated Outage

Total Primary-Firm Quantity Available Mdt/d

% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization)   

MLA DOT Replacement / Overlap with Job#1075438

June 16 – June27

3,234

0-10%

MLA DOT Replacement

June 28 – Aug 4

4,000

0-5%

 
TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 04/29/2025
Notice Eff Time: 09:46:28 CDT
Notice End Date:
Notice End Time:
Notice ID: 15619259
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 04/29/2025
Post Time: 09:46:28 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job #1077537 Station 115 MLA DOT Planned Outage and Maintenance Summary

Transco will be performing necessary maintenance associated with Job #1077537 on its 2025 Planned Outage and Maintenance Summary.  A pipeline outage is needed to perform a DOT replacement as required by regulation due to recent DOT Class Location changes near Station 115 on Mainline A adjacent to the station. This maintenance outage will impact the availability of transportation services moving south to north through Compressor Station 115.  The current schedule is to complete the work from June 16, 2025 through August 4, 2025.

During this period of planned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving south to north through the location may not be available.

Transco will be required to manage transportation services moving south to north through the TSB location listed below. The total quantity available will be contingent on system conditions during the maintenance period and is anticipated to be initially limited to the quantities indicated below. Transactions moving north to south through this location will not be impacted.

The receipt-based Throughput Section Boundary (TSB) at Mainline MP 1031 will be used to manage capacity availability, including any required changes to the expected total quantities available during this planned work indicated below. An updated Market and Production Area constraint notice will include the location and the available quantity of primary-firm transportation services during the indicated periods. 

 

TSB Name – Location  

Location ID  

Flow Direction  

Design Capacity (Mdt/d)  

Total Primary-Firm Quantity Available (Mdt/d) 

% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization)   

Mainline MP 1031

9013083 

South to North  

4,524

See Below

0-10%

 

Pipeline Maintenance

Estimated Outage

Total Primary-Firm Quantity Available Mdt/d

% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization)   

MLA DOT Replacement / Overlap with Job#1075438

June 16 – June27

3,234

0-10%

MLA DOT Replacement

June 28 – Aug 4

4,000

0-5%