Operations Planning Report V2 Aug 2026

TransColorado Gas Transmission 2mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  938939154-TRANSCOLORADO GAS TRANS CO LLC Critical: Y Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE Notice Eff Date/Time:  08/05/2026 3:29:31PM Notice End Date/Time:  08/06/2026 9:00:00am Post Date/Time:  8/5/2026 3:29:31 PM Notice ID: 123155 Reqrd Rsp:  1 Rsp Date/Time:  8/5/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  123133 Subject:  Operations Planning Report V2 Aug 2026
Notice Text:

TransColorado Pipeline Company

Operations Planning Report August, 2026

Re-issued August 5, 2026

Pipe

Start Date

End Date

County, ST

Scheduling Location

Maintenance List

Base Capacity (Dth)

Reduction (Dth)

Net (Dth)

Flow Indication

Update

TC

8/10/26

8/21/26

DOLORES, CO

250_ DOLORES C.S. TO MANCOS C.S.

Revision
End Date adjusted from 8-14 to 8/21
Scheduled Remediation Dig - Dolores to Red Mesa

355,000

355,000

0

TD1

Update

TC

8/10/26

8/21/26

DOLORES, CO

250_ DOLORES C.S. TO MANCOS C.S.

Revision
End Date adjusted from 8-14 to 8/21
Scheduled Remediation Dig - Dolores to Red Mesa

260,000

260,000

0

TD2

Update

TSP/TSP Name:  938939154-TRANSCOLORADO GAS TRANS CO LLC Critical: Y Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE Notice Eff Date/Time:  08/05/2026 3:29:31PM Notice End Date/Time:  08/06/2026 9:00:00am Post Date/Time:  8/5/2026 3:29:31 PM Notice ID: 123155 Reqrd Rsp:  1 Rsp Date/Time:  8/5/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  123133 Subject:  Operations Planning Report V2 Aug 2026
Notice Text:

TransColorado Pipeline Company

Operations Planning Report August, 2026

Re-issued August 5, 2026

Pipe

Start Date

End Date

County, ST

Scheduling Location

Maintenance List

Base Capacity (Dth)

Reduction (Dth)

Net (Dth)

Flow Indication

Update

TC

8/10/26

8/21/26

DOLORES, CO

250_ DOLORES C.S. TO MANCOS C.S.

Revision
End Date adjusted from 8-14 to 8/21
Scheduled Remediation Dig - Dolores to Red Mesa

355,000

355,000

0

TD1

Update

TC

8/10/26

8/21/26

DOLORES, CO

250_ DOLORES C.S. TO MANCOS C.S.

Revision
End Date adjusted from 8-14 to 8/21
Scheduled Remediation Dig - Dolores to Red Mesa

260,000

260,000

0

TD2

Update