Texas Gas Transmission Icon

Maintenance- Eunice Compressor Station

Texas Gas Transmission 23h ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name : Texas Gas Transmission, LLC

Category : Critical/Planned Service Outage

Notice Type Desc : Maintenance

Notice Stat Desc : Supersede

Notice ID : 5038404

Prior Notice : 5038394

Reqrd Rsp Desc : No response required

Subject : Maintenance- Eunice Compressor Station

TSP : 115972101

Post Date/Time : 07/09/2026 04:49:00 PM

Notice Effective Date/Time : 07/09/2026 04:50:00 PM

Notice End Date/Time : 08/15/2026 09:00:00 AM

Response Date/Time :

Critical : Y

Notice Text :

Superseding to update the Notice Text:
Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, the following meters will be limited to the following capacities
starting on Gas Day July 11, 2026:

Location 8758 (Gulf So - Patoutville) - 55,000 Dth/d
Location 9473 (Gulf So - Chacahoula) - 145,000 Dth/d
Location 9493 (Gulf So - S Gibson) - 125,000 Dth/d
Location 8040 (Florida Gas) - 25,000 Dth/d

Youngsville East (YVE) will be limited to 325,000 MMBtu/d of flow beginning July 9, 2026.

Please contact your customer service representative if you have any questions.

********************************************************************************************************************

Superseding to update the Notice Text:
Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, Youngsville East (YVE) will be limited to 325,000 MMBtu/d of flow
beginning July 9, 2026.

********************************************************************************************************************

Superseding to update the Notice Text:
Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, Youngsville East (YVE) will be limited to 340,000 MMBtu/d of
flow.

********************************************************************************************************************

Superseding to update the Compressor Station to Eunice instead of Youngsville.

********************************************************************************************************************

Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, Youngsville East (YVE) will be limited to 365,000 MMBtu/d of
flow.

Please contact your customer service representative if you have any questions.

Notice

Page 1 of 2

07/09/2026 4:50:02 PM

Internal purposes only: GCSR 41196

Page 2 of 2

07/09/2026 4:50:02 PM

Notice
TSP Name : Texas Gas Transmission, LLC
TSP : 115972101
Category : Critical/Planned Service Outage
Post Date/Time : 07/09/2026 04:49:00 PM
Notice Type Desc : Maintenance
Notice Effective Date/Time : 07/09/2026 04:50:00 PM
Notice Stat Desc : Supersede
Notice End Date/Time : 08/15/2026 09:00:00 AM
Notice ID : 5038404
Response Date/Time :
Prior Notice : 5038394
Critical : Y
Reqrd Rsp Desc : No response required
Subject : Maintenance- Eunice Compressor Station
Notice Text :
Superseding to update the Notice Text:
Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, the following meters will be limited to the following capacities
starting on Gas Day July 11, 2026:
Location 8758 (Gulf So - Patoutville) - 55,000 Dth/d
Location 9473 (Gulf So - Chacahoula) - 145,000 Dth/d
Location 9493 (Gulf So - S Gibson) - 125,000 Dth/d
Location 8040 (Florida Gas) - 25,000 Dth/d
Youngsville East (YVE) will be limited to 325,000 MMBtu/d of flow beginning July 9, 2026.
Please contact your customer service representative if you have any questions.
********************************************************************************************************************
Superseding to update the Notice Text:
Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, Youngsville East (YVE) will be limited to 325,000 MMBtu/d of flow
beginning July 9, 2026.
********************************************************************************************************************
Superseding to update the Notice Text:
Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, Youngsville East (YVE) will be limited to 340,000 MMBtu/d of
flow.
********************************************************************************************************************
Superseding to update the Compressor Station to Eunice instead of Youngsville.
********************************************************************************************************************
Texas Gas Transmission, LLC will be performing maintenance at the Eunice Compressor Station.
During this maintenance period, Youngsville East (YVE) will be limited to 365,000 MMBtu/d of
flow.
Please contact your customer service representative if you have any questions.
07/09/2026 4:50:02 PM
Page 1 of 2

Internal purposes only: GCSR 41196
07/09/2026 4:50:02 PM
Page 2 of 2