RESTRICTIONS FOR 08-03-2026 ID2
Tennessee Gas Pipeline 2mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Effective Intraday 2 Cycle (18:00) for the gas day of Monday, August 03, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 ON THE 500 lINE FROM STA 527 TO STA 542 FOR OVERTAKES OR UNDERDELIVIERS FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES
METER RESTRICTIONS
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to pipeline maintenance at delivery location; 54 Dths
· NMP/TGP Gillrina Road Nueces Delivery Meter (Pin 47799) - into PIP increases due to operational concerns
· GULFSTH/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 39 Dths
SEGMENT RESTRICTIONS
· STA 534 South Of Pool (Segment 530 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 450 Dths
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 82,000 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,494 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 8,409 Dths
· STA 110 South (Segment 187 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 297,970 Dths
· STA 315 (Segment 315 BH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 295,046 Dths
· STA 317 (Segment 317 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 64,424 Dths
· MLV 330 (Segment 324 FH) - through approx 75% of SOP increases due to nominations in excess of operational capacity; 53,056 Dths
· Z5hc North (Segment 299 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 329,167 Dths
· STA 245 (Segment 245 FH) - through approx 86% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 226,063 Dths
· STA 249 (Segment 249 FH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 77,446 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 98,639 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Effective Intraday 2 Cycle (18:00) for the gas day of Monday, August 03, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 ON THE 500 lINE FROM STA 527 TO STA 542 FOR OVERTAKES OR UNDERDELIVIERS FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES
METER RESTRICTIONS
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to pipeline maintenance at delivery location; 54 Dths
· NMP/TGP Gillrina Road Nueces Delivery Meter (Pin 47799) - into PIP increases due to operational concerns
· GULFSTH/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPss increases due to pipeline maintenance at delivery location; 39 Dths
SEGMENT RESTRICTIONS
· STA 534 South Of Pool (Segment 530 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 450 Dths
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 82,000 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,494 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 8,409 Dths
· STA 110 South (Segment 187 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 297,970 Dths
· STA 315 (Segment 315 BH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 295,046 Dths
· STA 317 (Segment 317 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 64,424 Dths
· MLV 330 (Segment 324 FH) - through approx 75% of SOP increases due to nominations in excess of operational capacity; 53,056 Dths
· Z5hc North (Segment 299 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 329,167 Dths
· STA 245 (Segment 245 FH) - through approx 86% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 226,063 Dths
· STA 249 (Segment 249 FH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 77,446 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 98,639 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.