Sta 563 & Sta 860 Project Changes

Tennessee Gas Pipeline 2w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  05/08/2026 10:48:42AM Notice End Date/Time:  05/09/2026 9:00:00am
Post Date/Time:  5/8/2026 10:48:42 AM Notice ID: 401182
Reqrd Rsp:  1 Rsp Date:  05/08/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Sta 563 & Sta 860 Project Changes
Notice Text:

Project Updates

 

"***Sta 563 Joelton:  Unit 2A - Solar Turbine Exchange

--6/8/26 through 6/19/26:  This project will require a unit outage, which will limit throughput through the station and result in restrictions based on customer nominations. 

***

Date Change, Previously scheduled 5/11/26 to 5/22/26.

………………………………"

 

"***Sta 860:  Annual ESD Test & Maintenance

--6/22/26 through 6/26/26:  This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. 

***

Date Change, Previously scheduled 6/8/26 to 6/12/26.

………………………………"

 

"***Sta 860:  Scrubber/Filter/Separator Clean, Inspect & Filter Change

--6/22/26 through 6/26/26:  This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. 

***

Date Change, Previously scheduled 6/8/26 to 6/12/26.

………………………………"

 

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  05/08/2026 10:48:42AM Notice End Date/Time:  05/09/2026 9:00:00am
Post Date/Time:  5/8/2026 10:48:42 AM Notice ID: 401182
Reqrd Rsp:  1 Rsp Date:  05/08/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Sta 563 & Sta 860 Project Changes
Notice Text:

Project Updates

 

"***Sta 563 Joelton:  Unit 2A - Solar Turbine Exchange

--6/8/26 through 6/19/26:  This project will require a unit outage, which will limit throughput through the station and result in restrictions based on customer nominations. 

***

Date Change, Previously scheduled 5/11/26 to 5/22/26.

………………………………"

 

"***Sta 860:  Annual ESD Test & Maintenance

--6/22/26 through 6/26/26:  This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. 

***

Date Change, Previously scheduled 6/8/26 to 6/12/26.

………………………………"

 

"***Sta 860:  Scrubber/Filter/Separator Clean, Inspect & Filter Change

--6/22/26 through 6/26/26:  This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. 

***

Date Change, Previously scheduled 6/8/26 to 6/12/26.

………………………………"

 

If you have any questions, please contact your Scheduler.