Tennessee Gas Pipeline Icon

RESTRICTIONS FOR 04-21-2026 TIMELY CYCLE

Tennessee Gas Pipeline 1mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/20/2026 3:16:34PM Notice End Date/Time:  04/21/2026 9:00:00am
Post Date/Time:  4/20/2026 3:16:34 PM Notice ID: 400777
Reqrd Rsp:  1 Rsp Date:  04/20/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-21-2026 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Tuesday, April 21, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 20,000 Dths

·         CARROLL/TGP County Home Carroll Delivery Meter (Pin 49198) - through approx 21% of IT due to nominations in excess of operational capacity; 8,025 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 65% of SIPss due to nominations in excess of operational capacity; 62,118 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through approx 71% of SOP due to nominations in excess of operational capacity; 12,244 Dths

·         STA 823 (Segment 823 BH) - through approx 58% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 33,634 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 20,000 Dths

·         STA 523 West (Segment 516 FH) - through approx 44% of SOP due to nominations in excess of operational capacity; 5,364 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 18,000 Dths

·         STA 307 (Segment 307 BH) - through approx 89% of SOP due to nominations in excess of operational capacity; 316,586 Dths

·         MLV 314 East (Segment 314 BH) - through approx 86% of SOP due to nominations in excess of operational capacity; 359,947 Dths

·         STA 315 (Segment 315 BH) - through approx 79% of SOP due to nominations in excess of operational capacity; 405,052 Dths

·         STA 317 (Segment 317 BH) - through approx 75% of SOP due to nominations in excess of operational capacity; 164,637 Dths

·         STA 321 (Segment 321 FH) - through approx 65% of SOP due to nominations in excess of operational capacity; 719,915 Dths

·         MLV 330 (Segment 324 FH) - through approx 52% of SOP due to nominations in excess of operational capacity; 297,705 Dths

·         MLV 336 East (Segment 336 FH) - through approx 93% of SOP due to nominations in excess of operational capacity; 42,251 Dths

·         STA 224 (Segment 224 FH) - through approx 67% of SOP due to nominations in excess of operational capacity; 134,877 Dths

·         Z5hc North (Segment 299 FH) - through approx 88% of SOP due to nominations in excess of operational capacity; 639,775 Dths

·         STA 245 (Segment 245 FH) - through approx 97% of SOP due to nominations in excess of operational capacity; 855,817 Dths

·         STA 249 (Segment 249 FH) - through approx 84% of SOP due to nominations in excess of operational capacity; 426,180 Dths

·         MLV 256 East (Segment 256 FH) - through approx 99% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 138,417 Dths

·         STA 261 Discharge East (Segment 261 FH) - through approx 37% of SOP due to nominations in excess of operational capacity; 55,635 Dths

·         MLV 273 (Segment 284 FH) - through approx 86% of SOP due to nominations in excess of operational capacity; 239,200 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/20/2026 3:16:34PM Notice End Date/Time:  04/21/2026 9:00:00am
Post Date/Time:  4/20/2026 3:16:34 PM Notice ID: 400777
Reqrd Rsp:  1 Rsp Date:  04/20/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-21-2026 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Tuesday, April 21, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 20,000 Dths

·         CARROLL/TGP County Home Carroll Delivery Meter (Pin 49198) - through approx 21% of IT due to nominations in excess of operational capacity; 8,025 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 65% of SIPss due to nominations in excess of operational capacity; 62,118 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through approx 71% of SOP due to nominations in excess of operational capacity; 12,244 Dths

·         STA 823 (Segment 823 BH) - through approx 58% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 33,634 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 20,000 Dths

·         STA 523 West (Segment 516 FH) - through approx 44% of SOP due to nominations in excess of operational capacity; 5,364 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 18,000 Dths

·         STA 307 (Segment 307 BH) - through approx 89% of SOP due to nominations in excess of operational capacity; 316,586 Dths

·         MLV 314 East (Segment 314 BH) - through approx 86% of SOP due to nominations in excess of operational capacity; 359,947 Dths

·         STA 315 (Segment 315 BH) - through approx 79% of SOP due to nominations in excess of operational capacity; 405,052 Dths

·         STA 317 (Segment 317 BH) - through approx 75% of SOP due to nominations in excess of operational capacity; 164,637 Dths

·         STA 321 (Segment 321 FH) - through approx 65% of SOP due to nominations in excess of operational capacity; 719,915 Dths

·         MLV 330 (Segment 324 FH) - through approx 52% of SOP due to nominations in excess of operational capacity; 297,705 Dths

·         MLV 336 East (Segment 336 FH) - through approx 93% of SOP due to nominations in excess of operational capacity; 42,251 Dths

·         STA 224 (Segment 224 FH) - through approx 67% of SOP due to nominations in excess of operational capacity; 134,877 Dths

·         Z5hc North (Segment 299 FH) - through approx 88% of SOP due to nominations in excess of operational capacity; 639,775 Dths

·         STA 245 (Segment 245 FH) - through approx 97% of SOP due to nominations in excess of operational capacity; 855,817 Dths

·         STA 249 (Segment 249 FH) - through approx 84% of SOP due to nominations in excess of operational capacity; 426,180 Dths

·         MLV 256 East (Segment 256 FH) - through approx 99% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 138,417 Dths

·         STA 261 Discharge East (Segment 261 FH) - through approx 37% of SOP due to nominations in excess of operational capacity; 55,635 Dths

·         MLV 273 (Segment 284 FH) - through approx 86% of SOP due to nominations in excess of operational capacity; 239,200 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.