Tennessee Gas Pipeline Icon

RESTRICTIONS FOR 04-11-2026 EC

Tennessee Gas Pipeline 2h ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/10/2026 7:09:13PM Notice End Date/Time:  04/11/2026 9:00:00am
Post Date/Time:  4/10/2026 7:09:13 PM Notice ID: 400559
Reqrd Rsp:  1 Rsp Date:  04/10/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-11-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Saturday, April 11, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR OVER-DELIVERIES INTO THE SYSTEM AND UNDER-TAKES OUT OF THE SYSTEM FOR VARIOUS PARTS OF THE SYSTEM (SEE NOTICE IDENTIFIER 400542) FOR ALL LMMAS, SAS ACTING AS BALANCING PARTIES AND LMPAS ONLY

METER RESTRICTIONS

·         ETP/TGP Wharton County Transport Ex Receipt Meter (Pin 411911) - through approx 11% of SA increases due to nominations in excess of operational capacity; 992 Dths

SEGMENT RESTRICTIONS

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 20,000 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,674 Dths

·         MLV 314 East (Segment 314 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 163,934 Dths

·         STA 315 (Segment 315 BH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 163,563 Dths

·         STA 317 (Segment 317 BH) - through approx 77% of SOP increases due to nominations in excess of operational capacity; 50,623 Dths

·         STA 321 (Segment 321 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 181,948 Dths

·         MLV 330 (Segment 324 FH) - through approx 7% of SOP increases due to nominations in excess of operational capacity; 6,255 Dths

·         Z5hc North (Segment 299 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 157,959 Dths

·         STA 245 (Segment 245 FH) - through approx 82% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 188,326 Dths

·         STA 249 (Segment 249 FH) - through approx 63% of SOP increases due to nominations in excess of operational capacity; 96,716 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 238,521 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

NONE

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

 

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/10/2026 7:09:13PM Notice End Date/Time:  04/11/2026 9:00:00am
Post Date/Time:  4/10/2026 7:09:13 PM Notice ID: 400559
Reqrd Rsp:  1 Rsp Date:  04/10/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-11-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Saturday, April 11, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR OVER-DELIVERIES INTO THE SYSTEM AND UNDER-TAKES OUT OF THE SYSTEM FOR VARIOUS PARTS OF THE SYSTEM (SEE NOTICE IDENTIFIER 400542) FOR ALL LMMAS, SAS ACTING AS BALANCING PARTIES AND LMPAS ONLY

METER RESTRICTIONS

·         ETP/TGP Wharton County Transport Ex Receipt Meter (Pin 411911) - through approx 11% of SA increases due to nominations in excess of operational capacity; 992 Dths

SEGMENT RESTRICTIONS

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 20,000 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 358,674 Dths

·         MLV 314 East (Segment 314 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 163,934 Dths

·         STA 315 (Segment 315 BH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 163,563 Dths

·         STA 317 (Segment 317 BH) - through approx 77% of SOP increases due to nominations in excess of operational capacity; 50,623 Dths

·         STA 321 (Segment 321 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 181,948 Dths

·         MLV 330 (Segment 324 FH) - through approx 7% of SOP increases due to nominations in excess of operational capacity; 6,255 Dths

·         Z5hc North (Segment 299 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 157,959 Dths

·         STA 245 (Segment 245 FH) - through approx 82% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 188,326 Dths

·         STA 249 (Segment 249 FH) - through approx 63% of SOP increases due to nominations in excess of operational capacity; 96,716 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 238,521 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

NONE

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

 

If you have any questions, please contact your Scheduler.