RESTRICTIONS FOR 05-01-2025 EC
Tennessee Gas Pipeline 12h ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 04/30/2025 7:14:40PM | Notice End Date/Time: 05/01/2025 9:00:00am |
Post Date/Time: 4/30/2025 7:14:40 PM | Notice ID: 394462 |
Reqrd Rsp: 1 | Rsp Date: 04/30/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 05-01-2025 EC |
Effective Evening Cycle (9:00) for the gas day of Thursday, May 01, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 SYSTEM WIDE (EXCLUDING ALL AREAS SOUTH OF STA 1 AND THE 500 LINE ONLY) FOR UNDER-TAKES FROM THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPps increases due to imbalance management quantity exceeded; 1,000 Dths
· TRANSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SIPss increases due to operational concerns; 2,179 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPps increases due to operational concerns; 55,000 Dths
· TRNSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 77% of SIPss increases due to nominations in excess of operational capacity; 11,426 Dths
SEGMENT RESTRICTIONS
· STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 40,725 Dths
· STA 523 East (Segment 523 FH) - through 100% of SIPps increases due to scheduled maintenance and nominations in excess of operational capacity; 504 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 817 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 910 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 438,714 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 307,509 Dths
· STA 315 (Segment 315 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 478,664 Dths
· STA 321 (Segment 321 FH) - through approx 78% of SOP increases due to nominations in excess of operational capacity and due to an emergent repair at STA 321 UNIT 5B; 284,655 Dths
· MLV 330 (Segment 324 FH) - through approx 36% of SOP increases due to nominations in excess of operational capacity; 23,755 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 300,378 Dths
· STA 245 (Segment 245 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 263,758 Dths
· STA 249 (Segment 249 FH) - through approx 73% of SOP increases due to nominations in excess of operational capacity; 161,163 Dths
· MLV 256 East (Segment 256 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 114,175 Dths
· MLV 273 (Segment 284 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 172,734 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 04/30/2025 7:14:40PM | Notice End Date/Time: 05/01/2025 9:00:00am |
Post Date/Time: 4/30/2025 7:14:40 PM | Notice ID: 394462 |
Reqrd Rsp: 1 | Rsp Date: 04/30/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 05-01-2025 EC |
Effective Evening Cycle (9:00) for the gas day of Thursday, May 01, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 SYSTEM WIDE (EXCLUDING ALL AREAS SOUTH OF STA 1 AND THE 500 LINE ONLY) FOR UNDER-TAKES FROM THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPps increases due to imbalance management quantity exceeded; 1,000 Dths
· TRANSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SIPss increases due to operational concerns; 2,179 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPps increases due to operational concerns; 55,000 Dths
· TRNSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 77% of SIPss increases due to nominations in excess of operational capacity; 11,426 Dths
SEGMENT RESTRICTIONS
· STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 40,725 Dths
· STA 523 East (Segment 523 FH) - through 100% of SIPps increases due to scheduled maintenance and nominations in excess of operational capacity; 504 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 817 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 910 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 438,714 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 307,509 Dths
· STA 315 (Segment 315 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 478,664 Dths
· STA 321 (Segment 321 FH) - through approx 78% of SOP increases due to nominations in excess of operational capacity and due to an emergent repair at STA 321 UNIT 5B; 284,655 Dths
· MLV 330 (Segment 324 FH) - through approx 36% of SOP increases due to nominations in excess of operational capacity; 23,755 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 300,378 Dths
· STA 245 (Segment 245 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 263,758 Dths
· STA 249 (Segment 249 FH) - through approx 73% of SOP increases due to nominations in excess of operational capacity; 161,163 Dths
· MLV 256 East (Segment 256 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 114,175 Dths
· MLV 273 (Segment 284 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 172,734 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.